| Owner | Filings | Most Recent |
|---|---|---|
| W28TH Development | 283 | 07/08/2026 |
| 1241 Broadway | 28 | 07/08/2026 |
| Met Tower Owner | 24 | 07/08/2026 |
| 322-326 7th Ave Realty | 17 | 03/21/2026 |
| Titan Industrial Services | 5 | 03/22/2026 |
| W 28th Renewal | 4 | 03/21/2026 |
| GDSNY | 1 | 03/22/2026 |
| Partner | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 11/18/2025 | $80.8M | — | W 28TH DEVELOPMENT LLC → 322 7TH AVE OWNER LLC | $922/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| Tricarico Architecture and Design | 5 | 11/20/2025 |
| Cosentini Associates | 60 | 08/21/2025 |
| GRM Consultants | 4 | 08/19/2025 |
| Fogarty Finger Architecture | 19 | 07/29/2025 |
| Leon Skvirsky PE | 2 | 07/03/2025 |
| Kiefer & Schuster Engineering | 1 | 05/14/2024 |
| Surface Design | 1 | 04/17/2023 |
| G. Blinn Consulting | 4 | 11/23/2021 |
| Gga Studios | 1 | 11/12/2021 |
| PCS Engineering | 1 | 04/29/2021 |
| HWL Engineering | 1 | 09/10/2020 |
| Structuretech New York | 1 | 07/20/2020 |
| Joel Phagoo P.E | 2 | 04/30/2019 |
| Baileys Engineering | 1 | 03/05/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| Metropolis Group | 168 | 03/21/2026 |
| Louis Striar | 8 | 03/21/2026 |
| Domani Consulting | 1 | 03/21/2026 |
| Building Brothers | 4 | 03/21/2026 |
| PCS Engineering | 1 | 03/21/2026 |
| Structuretech NY | 1 | 03/21/2026 |
| A1 Expediting Service | 12 | 03/21/2026 |
| Arra Architecture | 1 | 03/21/2026 |
| AE Design Solution | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Triton Construction Co | General Contractor | 41 | 07/08/2026 |
| TTM Group | Fire Protection | 18 | 07/08/2026 |
| S&E Bridge & Scaffold | Scaffold | 13 | 07/08/2026 |
| TT Mechanical | Plumbing | 12 | 07/08/2026 |
| Sage Builders | General Contractor | 10 | 07/08/2026 |
| Skyline Scaffolding Group | Scaffold | 8 | 07/08/2026 |
| Scientific Electl Conts | General Contractor | 5 | 03/22/2026 |
| Red Hook Sign and Electric | Sign hanger | 4 | 07/08/2026 |
| Practical Plumbing & Heating | Plumbing | 3 | 07/08/2026 |
| Titan Industrial Service | Scaffold | 3 | 03/21/2026 |
| Structuretech New York | Scaffold | 2 | 03/21/2026 |
| Active Signs | Sign hanger | 2 | 07/08/2026 |
| Alchemy Development | General Contractor | 2 | 07/08/2026 |
| TT Mechanical | Plumbing | 1 | 07/08/2026 |
| Delco Electrical | Electrical | 1 | 03/22/2026 |
| Fogarty Finger Architecture | General Contractor | 1 | 03/22/2026 |
| C.M. Richey Electrical Contracting | Electrical | 1 | 03/22/2026 |
| TT Mechanical | General Contractor | 1 | 03/22/2026 |
| Nash Electric Services | Electrical | 1 | 03/22/2026 |
| AL-Lectric Elect'l Contracting | Electrical | 1 | 03/22/2026 |
| A&H Express Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Dependable Mechanical | Fire Protection | 1 | 07/08/2026 |
| Practical Plumbing & Heating | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Metric Consulting and Ins | 1803 | 5 | 11/20/2025 |
| Domani Inspection Service | 843 | 68 | 08/21/2025 |
| PCS Engineering | 3745 | 1 | 04/29/2021 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sign | Signed-off | Red Hook Sign and Electric | 08/29/2025 |
| DOB NOW | Sign | Signed-off | Red Hook Sign and Electric | 08/29/2025 |
| DOB NOW | Sign | Signed-off | Red Hook Sign and Electric | 08/29/2025 |
| DOB NOW | Sign | Signed-off | Red Hook Sign and Electric | 08/29/2025 |
| DOB NOW | Sign | Permit Issued | Active Signs | 08/06/2025 |
| DOB NOW | Sign | Permit Issued | Active Signs | 08/06/2025 |
| DOB NOW | Sprinklers | Signed-off | Dependable Mechanical | 07/14/2025 |
| DOB NOW | General Construction | Signed-off | Sage Builders | 06/11/2025 |
| DOB NOW | Plumbing | Signed-off | A&H Express Plumbing & Heating | 04/23/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Alchemy Development | 04/15/2025 |
| DOB NOW | General Construction | Signed-off | Alchemy Development | 04/14/2025 |
| DOB NOW | Sprinklers | Signed-off | TTM Group | 03/17/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Triton Construction Co | 03/13/2025 |
| DOB NOW | General Construction | Signed-off | Triton Construction Co | 03/13/2025 |
| DOB NOW | Plumbing | Signed-off | TT Mechanical | 03/13/2025 |
| DOB NOW | Sprinklers | Signed-off | TTM Group | 01/30/2025 |
| DOB NOW | Plumbing | Signed-off | TT Mechanical | 01/30/2025 |
| DOB NOW | Plumbing | Signed-off | TT Mechanical | 01/30/2025 |
| DOB NOW | Sprinklers | Signed-off | TTM Group | 01/30/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Triton Construction Co | 01/27/2025 |
| DOB NOW | General Construction | Signed-off | Triton Construction Co | 01/27/2025 |
| DOB NOW | General Construction | Signed-off | Triton Construction Co | 01/27/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Triton Construction Co | 01/27/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Triton Construction Co | 12/05/2024 |
| DOB NOW | Sprinklers | Signed-off | TTM Group | 11/20/2024 |
| DOB NOW | Plumbing | Signed-off | TT Mechanical | 11/19/2024 |
| DOB NOW | General Construction | Signed-off | Triton Construction Co | 11/12/2024 |
| DOB NOW | General Construction | Signed-off | Triton Construction Co | 08/12/2024 |
| DOB NOW | Sprinklers | Signed-off | TTM Group | 08/08/2024 |
| DOB NOW | Plumbing | Signed-off | TT Mechanical | 08/08/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Triton Construction Co | 07/30/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Sage Builders | 07/11/2024 |
| DOB NOW | Sprinklers | Signed-off | Practical Plumbing & Heating | 06/24/2024 |
| DOB NOW | General Construction | Signed-off | Sage Builders | 06/20/2024 |
| DOB NOW | Plumbing | Signed-off | Practical Plumbing & Heating | 06/18/2024 |
| DOB NOW | Sprinklers | Signed-off | TTM Group | 06/13/2024 |
| DOB NOW | Plumbing | Signed-off | TT Mechanical | 06/13/2024 |
| DOB NOW | Structural | Signed-off | Sage Builders | 05/17/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Triton Construction Co | 05/07/2024 |
| DOB NOW | General Construction | Signed-off | Triton Construction Co | 05/06/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/05/2025 | Complete | Truephase Electrical Contractors | General Wiring |
| 07/17/2025 | Complete | Delco Electrical | General Wiring |
| 09/16/2024 | Permit Issued | AL-Lectric Elect'l Contracting | General Wiring |
| 03/18/2024 | Permit Issued | AL-Lectric Elect'l Contracting | General Wiring |
| 01/19/2024 | Complete | Delco Electrical | General Wiring |
| 02/24/2023 | Complete | Delco Electrical | 12 meters, 12 new_meters |
| 03/22/2022 | Complete | C.M. Richey Electrical Contracting | General Wiring |
| 02/08/2022 | Complete | C.M. Richey Electrical Contracting | General Wiring |
| 02/08/2022 | Complete | C.M. Richey Electrical Contracting | General Wiring |
| 02/08/2022 | Complete | C.M. Richey Electrical Contracting | General Wiring |
| 07/30/2020 | Complete | Jam Electrical | — |
| 05/15/2020 | Complete | Nash Electric Services | — |
| 05/11/2020 | Complete | Delco Electrical | — |
| 05/11/2020 | Complete | Delco Electrical | General Wiring |
| 02/26/2020 | Complete | Nash Electric Services | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/02/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/21/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/14/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/23/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/23/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/22/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 07/17/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 07/17/2025 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 07/08/2025 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 06/25/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/02/2025 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 05/20/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/14/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 05/08/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 04/24/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 04/21/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 04/21/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/03/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/24/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/24/2025 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 03/17/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/10/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/03/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/09/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/09/2024 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/21/2025 | HVAC-R and service water heating system controls | SAMI HAJJAR P.E | energy_progress |
| 11/21/2025 | HVAC-R and service water heating equipment | SAMI HAJJAR P.E | energy_progress |
| 11/21/2025 | Energy Code Compliance Inspections | SAMI HAJJAR P.E | progress |
| 11/21/2025 | Final | SAMI HAJJAR P.E | progress |
| 11/21/2025 | Fire-Resistant Penetrations and Joints | SAMI HAJJAR P.E | special |
| 11/21/2025 | Mechanical Systems | SAMI HAJJAR P.E | special |
| 11/19/2025 | Fire-Resistant Penetrations and Joints | SAMI HAJJAR P.E | special |
| 11/19/2025 | Mechanical Systems | SAMI HAJJAR P.E | special |
| 11/19/2025 | HVAC-R and service water heating system controls | SAMI HAJJAR P.E | energy_progress |
| 11/19/2025 | Final | SAMI HAJJAR P.E | progress |
| 11/19/2025 | Energy Code Compliance Inspections | SAMI HAJJAR P.E | progress |
| 11/19/2025 | HVAC-R and service water heating equipment | SAMI HAJJAR P.E | energy_progress |
| 08/22/2025 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 08/22/2025 | Post-installed Anchors | JOHN MCMONAGLE | special |
| 08/18/2025 | Final | GHANENDRA MISHRA | progress |
| 08/06/2025 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 08/06/2025 | Post-installed Anchors | JOHN MCMONAGLE | special |
| 07/25/2025 | Post-installed Anchors | JOHN MCMONAGLE | special |
| 07/25/2025 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 07/21/2025 | Final | GHANENDRA MISHRA | progress |
| 07/10/2025 | Public Assembly Emergency Lighting | JOHN MCMONAGLE | progress |
| 06/11/2025 | Fire-Resistant Penetrations and Joints | JOHN MCMONAGLE | special |
| 06/11/2025 | Post-installed Anchors | JOHN MCMONAGLE | special |
| 05/28/2025 | Final | LEON SKVIRSKY | progress |
| 05/06/2025 | Post-installed Anchors | JOHN MCMONAGLE | special |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| Joe and the Juice | Restaurant / Food Service | Floor 1 | Project M01237371 Project M01237372 Project M01237373 Project M01237374 Project M01199726 |
| Haymarket | Retail | Floor 1 | Project M01232291 |
| GDSNY | Office | Cellar, Floors 1–3, 7, 8 | Project M01050192 Project M01050185 Project M01048813 Project M01024347 Project M00662521 Project M00662596 |
| Bliss Fasman | Office | Floor 1 | Project M00936885 |
| FD Wellness | Office | Floor 7 | Project M00651938 Project M00662549 Project M00662566 |