| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q00061293 ↗ | 300 KENMORE ROAD QUEENS | Alteration | Signed-off | 07/17/2018 | 04/08/2022 | Design SOUTH BAY ENGINEERING PLLC Contractor CENTRAL CONSTRUCTION MANAGEMENT | TO CONSTRUCT A 8 FOOT PLY WOOD FENCE FOR A DEMOLITION OF A POOL HOUSE |
| M00263254 ↗ | 17 FT GEORGE HILL MANHATTAN | Alteration | Signed-off | 11/12/2019 | 01/12/2022 | Design NICHOLAS J. DEFELICE, P.E. Contractor CENTRAL CONSTRUCTION MANAGEMENT | PAA to revise the following: EQ-100.01 ADDED NEW SECTIONS MARKERS AND MODIFIED SIDEWALK SHED LAY-OUT, EQ-105.00 ADDED NEW SECTION SHOWING … |
| M00172836 ↗ | 109 AUDUBON AVENUE MANHATTAN | Alteration | Signed-off | 06/04/2019 | 03/19/2021 | Design NICHOLAS J. DEFELICE, P.E. Contractor CENTRAL CONSTRUCTION MANAGEMENT | EQ-100.01 Showing the location for the reconfiguration of the sidewalk shed at the west elevation EQ-101.01 Showing in the elevation the new… |
| M00260166 ↗ | 120 CABRINI BOULEVARD MANHATTAN | Alteration | Signed-off | 11/20/2019 | 03/19/2021 | Design NICHOLAS J. DEFELICE, P.E. Contractor CENTRAL CONSTRUCTION MANAGEMENT | Installation of temporary sidewalk shed per plans submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress… |
| M00263521 ↗ | 422 EAST 72 STREET MANHATTAN | Alteration | Permit Issued | 11/12/2019 | 03/19/2021 | Design NICHOLAS J. DEFELICE, P.E. Contractor CENTRAL CONSTRUCTION MANAGEMENT | Add additional sidewalk shed as per drawings |
| M00353897 ↗ | 1463 2 AVENUE MANHATTAN | Alteration | Signed-off | 06/02/2020 | 03/19/2021 | Design NICHOLAS J. DEFELICE, P.E. Owner CENTRAL CONST MANAGEMENT Contractor CENTRAL CONSTRUCTION MANAGEMENT | Installation of heavy duty sidewalk shed for remedial repairs. Live load 300PSF. Sidewalk shed shall comply with chapter # 33 of the 2008 co… |
| Person | Filings | Most recent |
|---|---|---|
| CATALINA HIDALGO | 3 | 08/07/2020 |
| Name | Projects together | Most recent |
|---|---|---|
| NICHOLAS J. DEFELICE, P.E. | 11 | 11/18/2020 |
| SOUTH BAY ENGINEERING PLLC | 1 | 07/17/2018 |
| Name | Projects together | Most recent |
|---|---|---|
| CENTRAL CONSTRUCTION MANA | 11 | 11/18/2020 |
| DJM NYC, LLC | 8 | 08/07/2020 |
| Name | Projects together | Most recent |
|---|---|---|
| CENTRAL CONSTRUCTION MAN* | 8 | 11/18/2020 |
| CENTRAL CONST MANAGEMENT | 2 | 06/02/2020 |
| CENTRAL CONSTRUCTION MANA | 1 | 07/17/2018 |
| DJM NYC LLC | 1 | 12/16/2019 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q00061293 ↗ | 300 KENMORE ROAD QUEENS | Alteration | Signed-off | 07/17/2018 | 04/08/2022 | Design SOUTH BAY ENGINEERING PLLC Contractor CENTRAL CONSTRUCTION MANAGEMENT | TO CONSTRUCT A 8 FOOT PLY WOOD FENCE FOR A DEMOLITION OF A POOL HOUSE |
| M00263254 ↗ | 17 FT GEORGE HILL MANHATTAN | Alteration | Signed-off | 11/12/2019 | 01/12/2022 | Design NICHOLAS J. DEFELICE, P.E. Contractor CENTRAL CONSTRUCTION MANAGEMENT | PAA to revise the following: EQ-100.01 ADDED NEW SECTIONS MARKERS AND MODIFIED SIDEWALK SHED LAY-OUT, EQ-105.00 ADDED NEW SECTION SHOWING … |
| M00172836 ↗ | 109 AUDUBON AVENUE MANHATTAN | Alteration | Signed-off | 06/04/2019 | 03/19/2021 | Design NICHOLAS J. DEFELICE, P.E. Contractor CENTRAL CONSTRUCTION MANAGEMENT | EQ-100.01 Showing the location for the reconfiguration of the sidewalk shed at the west elevation EQ-101.01 Showing in the elevation the new… |
| M00260166 ↗ | 120 CABRINI BOULEVARD MANHATTAN | Alteration | Signed-off | 11/20/2019 | 03/19/2021 | Design NICHOLAS J. DEFELICE, P.E. Contractor CENTRAL CONSTRUCTION MANAGEMENT | Installation of temporary sidewalk shed per plans submitted. Work shall comply with 2014 building codes chapter 33. No change in use, egress… |
| M00263521 ↗ | 422 EAST 72 STREET MANHATTAN | Alteration | Permit Issued | 11/12/2019 | 03/19/2021 | Design NICHOLAS J. DEFELICE, P.E. Contractor CENTRAL CONSTRUCTION MANAGEMENT | Add additional sidewalk shed as per drawings |
| M00353897 ↗ | 1463 2 AVENUE MANHATTAN | Alteration | Signed-off | 06/02/2020 | 03/19/2021 | Design NICHOLAS J. DEFELICE, P.E. Owner CENTRAL CONST MANAGEMENT Contractor CENTRAL CONSTRUCTION MANAGEMENT | Installation of heavy duty sidewalk shed for remedial repairs. Live load 300PSF. Sidewalk shed shall comply with chapter # 33 of the 2008 co… |
| M00256801 ↗ | 430 EAST 57 STREET MANHATTAN | Alteration | Permit Issued | 11/01/2019 | 11/02/2020 | Design NICHOLAS J. DEFELICE, P.E. Contractor CENTRAL CONSTRUCTION MANAGEMENT | Installation of heavy duty sidewalk shed for remedial repairs. Live load 300PSF. Sidewalk shed shall comply with chapter #33 of the 2008 cod… |
| M00261288 ↗ | 1212 5 AVENUE MANHATTAN | Alteration | Permit Issued | 11/07/2019 | 10/21/2020 | Design NICHOLAS J. DEFELICE, P.E. Contractor CENTRAL CONSTRUCTION MANAGEMENT | Drawings have been amended to add additional sidewalk shed on the east elevation of the building. |
| M00349645 ↗ | 120 CABRINI BOULEVARD MANHATTAN | Alteration | Permit Issued | 05/15/2020 | 10/21/2020 | Design NICHOLAS J. DEFELICE, P.E. Owner CENTRAL CONST MANAGEMENT Contractor CENTRAL CONSTRUCTION MANAGEMENT | Erect, maintain, and dismantle of scaffold for facade repairs as per plans filed herewith. No change in use, egress or occupancy. |
| M00282382 ↗ | 28 5 AVENUE MANHATTAN | Alteration | Signed-off | 12/16/2019 | 08/19/2020 | Design NICHOLAS J. DEFELICE, P.E. Owner DJM NYC LLC Contractor DJM NYC, LLC | Erect, maintain, and dismantle of scaffold for facade repairs as per plans filed herewith. No change in use, egress or occupancy. |
| M00175460 ↗ | 109 AUDUBON AVENUE MANHATTAN | Alteration | Signed-off | 06/07/2019 | 07/08/2020 | Design NICHOLAS J. DEFELICE, P.E. Contractor CENTRAL CONSTRUCTION MANAGEMENT | We are submitting a PAA to amend the following pages: EQ-103.02 Showing location for the installation of material hoist and adding aluminum… |
| M00187241 ↗ | 1107 5 AVENUE MANHATTAN | Alteration | Permit Issued | 07/09/2019 | 08/02/2019 | Design NICHOLAS J. DEFELICE, P.E. Contractor CENTRAL CONSTRUCTION MANAGEMENT | Filing for installation of pipe scaffolding on behalf of contractor |
| Building | Filings | Most Recent |
|---|---|---|
| 17 FT GEORGE HILL ↗ | 1 | 08/07/2020 |
| 1463 2 AVENUE ↗ | 1 | 06/02/2020 |
| 422 EAST 72 STREET ↗ | 3 | 05/18/2020 |
| 1212 5 AVENUE ↗ | 1 | 05/15/2020 |
| 120 CABRINI BOULEVARD ↗ | 1 | 05/15/2020 |
| 28 5 AVENUE ↗ | 1 | 12/16/2019 |
| 120 CABRINI BOULEVARD ↗ | 1 | 11/06/2019 |
| 430 EAST 57 STREET ↗ | 1 | 10/31/2019 |
| 1107 5 AVENUE ↗ | 1 | 07/01/2019 |
| 109 AUDUBON AVENUE ↗ | 2 | 06/03/2019 |
| 300 KENMORE ROAD ↗ | 1 | 07/12/2018 |