💬 Discuss this project
2008Year Built
40Stories
O4Building Class
C6-4Zoning
843,564 sfGross Floor Area
1Units
LL97 Covered0 Active ViolationsFISP: SAFE
Office, 20+ stories, with or without commercial · Owner of record: Gladden Properties · 46,442 sf lot · 18.16 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Floor 38Squarepoint25p · 5 filings · 20 docs
Floor 37
Floor 36
Floor 35
Floor 34Aperture Investors26p · 4 filings · 14 docs
Floor 33LFG America71p · 6 filings · 20 docs
Floor 32Squarepoint87p · 4 filings · 20 docs
Floor 31LS Power92p · 5 filings · 20 docs
Floor 30LS Power, Glazer +1121p · 10 filings · 20 docs
Floor 29
Floor 28
Floor 27
Floor 26Redwood Capital Management, Soros Fund ManagementUnder Construction51p · 8 filings · 20 docs
Floor 25Boston Properties30p · 3 filings · 20 docs
Floor 24
Floor 23
Floor 22Morrison & Foerster19p · 3 filings · 9 docs
Floor 21
Floor 20
Floor 19
Floor 18
Floor 17
Floor 16Mechanical ductwork installation and demolition12p · 3 filings · 11 docs
Floor 15Squarepoint60p · 4 filings · 20 docs
Floor 14Arnold & Porter26p · 3 filings · 15 docs
Floor 13Squarepoint, McCarter & English57p · 5 filings · 20 docs
Floor 12
Floor 11Arnold & Porter26p · 3 filings · 15 docs
Floor 10Arnold & Porter26p · 3 filings · 15 docs
Floor 9Arnold & Porter26p · 3 filings · 15 docs
Floor 8
Floor 7
Floor 6
Floor 5Arnold & Porter28p · 3 filings · 15 docs
Floor 4
Floor 3
Floor 2Spyscape, Arnold & Porter35p · 14 filings · 20 docs
Floor 1Naya, Click-fil-a71p · 16 filings · 20 docs
Mezzanine4p · 5 filings · 10 docs
CellarMorrison & Foerster33p · 5 filings · 14 docs
Sub-CellarArnold & Porter14p · 3 filings · 11 docs
Site & exteriorNaya, TD Bank +16p · 4 filings · 11 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Boston Properties-Lexington Ave44203/21/2026
BXP24407/08/2026
Gladden Properties7103/22/2026
Hearst Communications3103/21/2026
BP 347 Madison Associates407/08/2026
Fairstead Capital203/22/2026
Lyfe103/21/2026
599 Lexington Ave103/21/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Gillman Consulting19403/21/2026
Municipal Building Consultants103/21/2026
JP Expedite403/21/2026
D R Brown403/21/2026
Universal Signs Service203/21/2026
Anzalone Architecture403/21/2026
All in Permit Consultants103/21/2026
Milrose Consultants103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Icon InteriorsGeneral Contractor1707/08/2026
Petretti & AssociatesGeneral Contractor1407/08/2026
Clune Construction CoGeneral Contractor1207/08/2026
JT Magen & CompanyGeneral Contractor806/28/2026
Aggressive Fire ProtectionPlumbing503/22/2026
Tri-Star ConstructionGeneral Contractor507/08/2026
Demar PlumbingPlumbing507/08/2026
Concept Construction ServiceGeneral Contractor403/21/2026
Americon ConstructionGeneral Contractor403/21/2026
Patriot ElectricElectrical403/22/2026
Structure ToneGeneral Contractor403/21/2026
Full Capacity FireFire Protection407/08/2026
Lawrence J. LevineFire Protection403/21/2026
Abco-Peerless SprinklerFire Protection307/08/2026
Cooper WorksGeneral Contractor307/08/2026
Gannon ContractingGeneral Contractor307/08/2026
Demar PlumbingFire Protection307/08/2026
Mass ContractingGeneral Contractor307/08/2026
Par Fire ProtectionPlumbing303/22/2026
Par Plumbing CoPlumbing207/08/2026
Sirina Fire ProtectionFire Protection207/08/2026
Nationwide MechanicalPlumbing207/08/2026
Tower Fire ProtectionFire Protection207/08/2026
Mill Brook Fire ProtectionFire Protection207/08/2026
William C. Gerakaris P&HPlumbing207/08/2026
Connelly & Sons PlumbingPlumbing207/08/2026
Demar Plumbingspecialty_contractor203/21/2026
Allstate SprinklerFire Protection207/08/2026
Signs CadSign hanger207/08/2026
Ultimate Signs & Designs CoSign hanger207/08/2026
Atlas-Acon Electric ServiceElectrical203/22/2026
Preferred Sprinkler and MechanicalFire Protection207/08/2026
Preferred MechanicalPlumbing106/28/2026
Doumas ElectricElectrical103/22/2026
Ecny Electrical ContractorsElectrical103/22/2026
Konsker ElectricElectrical103/22/2026
Lmec ElectricElectrical103/22/2026
Philip A. RobinsonElectrical103/21/2026
Strand Electric CoElectrical103/22/2026
Donnelly Mechanicalspecialty_contractor107/08/2026
Howard M.haimesGeneral Contractor107/08/2026
Winick ProductionsGeneral Contractor107/08/2026
National MaintenanceSign hanger107/08/2026
Universal Signs & ServiceSign hanger107/08/2026
A&A PlumbingPlumbing107/08/2026
Accurate MechanicalPlumbing107/08/2026
Accurate MechanicalFire Protection107/08/2026
Aggressive Fire ProtectionFire Protection110/04/2026
Arco Plumbing and HeatingPlumbing107/08/2026
Enobrac PlumbingPlumbing107/08/2026
Enobrac PlumbingFire Protection107/08/2026
Lipsky & RosenthalPlumbing107/08/2026
Par Fire ProtectionFire Protection107/08/2026
All State Electric CnstctElectrical103/22/2026
PSI PartnersFire Protection107/08/2026
Soh Par SprinklerFire Protection107/08/2026
Tristate Plumbing ServicesPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Alan Margolin & Associates4231005/18/2026
MEP Inspections1102302/16/2026
Atlas ATC Engineering80111202/12/2026
Codegreen510506/09/2025
DNA Controlled Inspection554804/23/2025
AK Engineering678103/18/2025
Engineering Building Service7303403/05/2025
Socotec Engineering4983407/18/2024
Metrospec Sia6420306/13/2024
Consulting and Testing SE6152311/21/2023
Atlantic Engineeringlabor13811305/18/2022
Special Inspection Services1200504/09/2021
Delta Testing Labs687211/06/2019
Building Lifecycle
All (300)Filed (77)Permit Issued (73)Signed Off (44)Facade (FISP) (3)Violation (8)Inspection (57)Objection (8)Special Inspection (30)
09/22/2026
Signed off — Alteration
Modifications to sprinkler heads and related piping as per plans. No change in use, egress or occupancy.
M01308368-S1
09/21/2026
Signed off — Alteration
Removal of existing plumbing fixtures as per plan. No change in use, egress or occupancy.
M01291062-S2
09/21/2026
Signed off — Alteration
Removal of existing plumbing fixtures as per plan. No change in use, egress or occupancy.
M01291062-S3
09/21/2026
Signed off — Alteration
Modifications to sprinkler heads and related piping as per plans. No change in use, egress or occupancy.
M01308368-S3
09/21/2026
Signed off — Alteration
Modifications to sprinkler heads and related piping as per plans. No change in use, egress or occupancy.
M01308368-S2
09/21/2026
Signed off — Alteration
Removal of existing plumbing fixtures as per plan. No change in use, egress or occupancy.
M01291062-S1
09/17/2026
Signed off — Alteration
Modifications to sprinkler heads and related piping as per plans. No change in use, egress or occupancy.
M01308368-I1
09/17/2026
Signed off — Alteration
Removal of existing plumbing fixtures as per plan. No change in use, egress or occupancy.
M01291062-I1
07/20/2026
Signed off — Alteration
M01064851-I1
07/02/2026
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
06/26/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
06/26/2026
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
06/10/2026
Signed off — Alteration
Modification to interior partitions, ceilings, doors and finishes as shown on drawings filed herewith. No change in use, egress or occupancy.
M01026334-I1
05/21/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
05/19/2026
Special inspection requirement — HVAC-R and service water heating system controls
Young Suh
05/19/2026
Special inspection requirement — Sprinkler Systems
Young Suh
05/19/2026
Special inspection requirement — Mechanical Systems
Young Suh
05/19/2026
Special inspection requirement — HVAC-R and service water heating equipment
Young Suh
05/19/2026
Special inspection requirement — Lighting controls
Young Suh
05/19/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Young Suh
05/19/2026
Special inspection requirement — Final
Young Suh
05/19/2026
Special inspection requirement — Interior lighting power
Young Suh
05/18/2026
Filed — Alteration
Modifications to sprinkler heads and related piping as per plans. No change in use, egress or occupancy.
M01308368-P4
05/18/2026
Filed — Alteration
Modifications to sprinkler heads and related piping as per plans. No change in use, egress or occupancy.
M01308368-P2
05/18/2026
Filed — Alteration
Modifications to sprinkler heads and related piping as per plans. No change in use, egress or occupancy.
M01308368-P3
05/08/2026
Signed off — Alteration
Modifications to sprinkler heads and related piping as per plans. No change in use, egress or occupancy.
M01243466-I1
05/08/2026
Special inspection requirement — Mechanical Systems
Young Suh
05/08/2026
Special inspection requirement — Interior lighting power
Young Suh
05/08/2026
Special inspection requirement — HVAC-R and service water heating equipment
Young Suh
05/08/2026
Special inspection requirement — HVAC-R and service water heating system controls
Young Suh
05/08/2026
Special inspection requirement — Lighting controls
Young Suh
05/08/2026
Special inspection requirement — Sprinkler Systems
Young Suh
05/08/2026
Special inspection requirement — Final
Young Suh
05/08/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Young Suh
04/10/2026
Permit issued — Sprinklers
M01337440-S2-EW-SP
03/26/2026
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
03/26/2026
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
02/27/2026
Permit issued — Mechanical Systems
M01337440-S1-MS
02/27/2026
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
02/20/2026
Permit issued — General Construction
M01337440-I1-GC
02/16/2026
Filed — Alteration
M01337440-S1
02/16/2026
Filed — Alteration
M01337440-S2
02/13/2026
Filed — Alteration
M01337440-I1
02/12/2026
Filed — Alteration
M01026357-P1
02/12/2026
Signed off — Alteration
Addition of new cold water piping to a new installed electric storage type water heater as shown on plans filed herewith. No change in use, egress or occupancy.
M01026375-I1
01/21/2026
Signed off — Alteration
Structural work associated with slab removal as per plans filed herewith. No change in use, egress or occupancy
M01064882-I1
01/20/2026
Signed off — Alteration
Modifications to sprinkler heads and related piping as per plans. No change in use, egress or occupancy.
M01243466-S2
01/20/2026
Signed off — Alteration
Modifications to sprinkler heads and related piping as per plans. No change in use, egress or occupancy.
M01243466-S1
01/14/2026
Special inspection requirement — Interior lighting power
Nicolas Crosetto
01/14/2026
Special inspection requirement — Duct leakage testing, insulation and design
Nicolas Crosetto
01/14/2026
Special inspection requirement — Lighting controls
Nicolas Crosetto
01/14/2026
Special inspection requirement — Sprinkler Systems
Nicolas Crosetto
01/14/2026
Special inspection requirement — Mechanical Systems
Nicolas Crosetto
01/14/2026
Special inspection requirement — Final
Nicolas Crosetto
01/06/2026
Special inspection requirement — Final
RONALD GRAPIN
01/06/2026
Special inspection requirement — Mechanical Systems
RONALD GRAPIN
01/06/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
RONALD GRAPIN
01/06/2026
Special inspection requirement — Lighting controls
RONALD GRAPIN
01/06/2026
Special inspection requirement — HVAC-R and service water heating system controls
RONALD GRAPIN
01/06/2026
Special inspection requirement — Duct leakage testing, insulation and design
RONALD GRAPIN
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersPermit IssuedFull Capacity Fire04/10/2026
DOB NOWMechanical SystemsPermit IssuedTri-Star Construction02/27/2026
DOB NOWGeneral ConstructionPermit IssuedTri-Star Construction02/20/2026
DOB NOWPlumbingSigned-offPreferred Mechanical12/03/2025
DOB NOWGeneral ConstructionSigned-offIcon Interiors12/03/2025
DOB NOWSprinklersSigned-offPreferred Sprinkler and Mechanical12/03/2025
DOB NOWMechanical SystemsSigned-offIcon Interiors11/21/2025
DOB NOWGeneral ConstructionSigned-offIcon Interiors10/06/2025
DOB NOWPlumbingSigned-offPar Plumbing Co10/03/2025
DOB NOWSprinklersSigned-offSoh Par Sprinkler10/03/2025
DOB NOWMechanical SystemsSigned-offIcon Interiors10/02/2025
DOB NOWSprinklersSigned-offLawrence J. Levine07/16/2025
DOB NOWMechanical SystemsSigned-offIcon Interiors07/09/2025
DOB NOWGeneral ConstructionSigned-offIcon Interiors07/09/2025
DOB NOWMechanical SystemsSigned-offJT Magen & Company07/01/2025
DOB NOWStructuralSigned-offJT Magen & Company06/26/2025
DOB NOWGeneral ConstructionSigned-offJT Magen & Company06/26/2025
DOB NOWPlumbingSigned-offConnelly & Sons Plumbing04/08/2025
DOB NOWGeneral ConstructionSigned-offTri-Star Construction04/01/2025
DOB NOWMechanical SystemsSigned-offTri-Star Construction04/01/2025
DOB NOWSignSigned-offUniversal Signs & Service01/21/2025
DOB NOWPlumbingSigned-offA&A Plumbing01/13/2025
DOB NOWSprinklersSigned-offFull Capacity Fire12/20/2024
DOB NOWMechanical SystemsSigned-offMass Contracting12/10/2024
DOB NOWGeneral ConstructionSigned-offMass Contracting12/09/2024
DOB NOWSprinklersSigned-offFull Capacity Fire11/27/2024
DOB NOWPlumbingPermit IssuedWilliam C. Gerakaris P&H11/25/2024
DOB NOWMechanical SystemsSigned-offGannon Contracting11/22/2024
DOB NOWGeneral ConstructionSigned-offGannon Contracting11/22/2024
DOB NOWGeneral ConstructionSigned-offWinick Productions09/26/2024
DOB NOWSprinklersSigned-offAccurate Mechanical09/24/2024
DOB NOWPlumbingPermit IssuedAnthony Disabato08/15/2024
DOB NOWPlumbingSigned-offConnelly & Sons Plumbing08/12/2024
DOB NOWMechanical SystemsSigned-offJT Magen & Company07/30/2024
DOB NOWGeneral ConstructionSigned-offCooper Works07/29/2024
DOB NOWMechanical SystemsSigned-offCooper Works07/29/2024
DOB NOWStructuralSigned-offJT Magen & Company07/26/2024
DOB NOWGeneral ConstructionSigned-offJT Magen & Company07/26/2024
DOB NOWSprinklersSigned-offMora Fire Protection05/01/2024
DOB NOWPlumbingSigned-offWilliam C. Gerakaris P&H04/30/2024
+ 60 more permits on file
3 projects · most recent 05/18/2026
Air Conditioning Systems Heating and Air Conditioning Systems
FiledStatusContractorScopeMake / Model / Capacity
05/18/2026Signed-offIcon InteriorsHeating and Air Conditioning Systems
Heat / Cool
Above Air MCW-011S1-4-00ERH-EC-00-UF0-XS 42,300 BTU · Crac Unit ×4
Florida Heat Pump CL024 800 CFM · Wshp ×2
07/07/2025Signed-offIcon InteriorsAir Conditioning Systems
Cooling
Vertiv DME020E-PCNS007 18,800 BTU · Crac Unit ×1
04/23/2025Signed-offJT Magen & CompanyAir Conditioning Systems
Cooling
Water Furnace UVH060 49,130 BTU · Wshp ×2
VV048 41,999 BTU · Wshp ×2
V7AH072ER 49,130 BTU · Wshp ×2
VSAH042BS3AB4D 41,999 BTU · Wshp ×2
7 projects · most recent 05/18/2026
FiledStatusContractorScope
05/18/2026Signed-offPreferred Sprinkler and Mechanical582 heads
10/01/2025Signed-offSoh Par Sprinkler180 heads
07/07/2025Signed-offPar Fire Protection16 heads
11/19/2024Signed-offFull Capacity Fire—
04/29/2024Signed-offPSI Partners34 heads
02/26/2020Signed-offAllstate Sprinkler7 heads
02/12/2020Signed-offAbco Peerless Sprinkler148 heads
6 projects · most recent 05/18/2026
Water/Sanitary Gas
FiledStatusContractorScope
05/18/2026Signed-offPreferred MechanicalWater/Sanitary
10/01/2025Signed-offPar Plumbing CoWater/Sanitary
07/07/2025———
04/23/2025Signed-offConnelly & Sons PlumbingWater/Sanitary
03/06/2025Permit IssuedWilliam C. Gerakaris P&HWater/Sanitary
11/06/2019Permit IssuedDemar PlumbingGas, Water/Sanitary
25 projects · most recent 07/02/2026
General Wiring Lighting
FiledStatusContractorScope
07/02/2026Permit IssuedAtlas-Acon Electric Service1 meters
06/22/2026CompleteCampbell & Dawes Ltd ElectricGeneral Wiring
05/20/2026Permit IssuedAvalon ElectricGeneral Wiring
10/09/2025CompleteKleinknecht Electric CoGeneral Wiring
07/15/2025CompleteP.E. StoneGeneral Wiring
07/11/2025Permit IssuedAtlas-Acon Electric Service1 meters
06/17/2025CompleteTroon Electric of New YorGeneral Wiring
11/25/2024CompleteAllstate ElectricGeneral Wiring
08/12/2024CompleteKleinknecht Electric CoGeneral Wiring
08/07/2024CompleteGreen Apple Electrical ServicesGeneral Wiring
05/17/2024Permit IssuedLmec ElectricGeneral Wiring, Lighting
03/29/2024CompleteGalaxy Electric—
02/26/2024CompleteAtlas-Acon Electric Service1 meters
12/04/2023CompletePolo Electric Corp D/B/AGeneral Wiring
08/31/2023CompleteAtlas-Acon Electric Service1 meters
▾Field Inspections (DOB CAP) — 57
DateTypeResultReport
07/02/2026Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/26/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
06/26/2026Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
05/21/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/26/2026Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/26/2026Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
02/27/2026Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/23/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
12/17/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
11/20/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/13/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
11/13/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
10/30/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/15/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/09/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/28/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
08/20/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/15/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
08/15/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/19/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
03/14/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
03/14/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/14/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/07/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
03/07/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
Latest 25 of 57.
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
05/19/2026Mechanical SystemsYoung Suhspecial
05/19/2026FinalYoung Suhprogress
05/19/2026HVAC-R and service water heating equipmentYoung Suhenergy_progress
05/19/2026HVAC-R and service water heating system controlsYoung Suhenergy_progress
05/19/2026Interior lighting powerYoung Suhenergy_progress
05/19/2026HVAC-R and service water piping design and insulationYoung Suhenergy_progress
05/19/2026Sprinkler SystemsYoung Suhspecial
05/19/2026Lighting controlsYoung Suhenergy_progress
05/08/2026Interior lighting powerYoung Suhenergy_progress
05/08/2026Lighting controlsYoung Suhenergy_progress
05/08/2026HVAC-R and service water heating system controlsYoung Suhenergy_progress
05/08/2026HVAC-R and service water heating equipmentYoung Suhenergy_progress
05/08/2026HVAC-R and service water piping design and insulationYoung Suhenergy_progress
05/08/2026FinalYoung Suhprogress
05/08/2026Mechanical SystemsYoung Suhspecial
05/08/2026Sprinkler SystemsYoung Suhspecial
01/14/2026Lighting controlsNicolas Crosettoenergy_progress
01/14/2026Interior lighting powerNicolas Crosettoenergy_progress
01/14/2026Duct leakage testing, insulation and designNicolas Crosettoenergy_progress
01/14/2026Sprinkler SystemsNicolas Crosettospecial
01/14/2026FinalNicolas Crosettoprogress
01/14/2026Mechanical SystemsNicolas Crosettospecial
01/06/2026HVAC-R and service water piping design and insulationRONALD GRAPINenergy_progress
01/06/2026Mechanical SystemsRONALD GRAPINspecial
01/06/2026FinalRONALD GRAPINprogress
Latest 25 of 150.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Redwood Capital ManagementOfficeFloor 26
Project M01337440 Alteration · Permit Entire · 02/13/2026
Project M00473666 Alteration · LOC Issued · 04/09/2021
Project M00475488 Alteration · LOC Issued · 04/05/2021
Project M00477430 Alteration · LOC Issued · 04/05/2021
Project M00478280 Alteration · LOC Issued · 04/05/2021
SquarepointOfficeFloors 13, 15, 32, 38
Project M01308368 Alteration · LOC Issued · 11/14/2025
Project M01291062 Alteration · LOC Issued · 10/01/2025
Project M01243466 Alteration · LOC Issued · 07/01/2025
Project M08031691 Alteration · LOC Issued · 12/27/2022
Project M08031794 Alteration · LOC Issued · 12/27/2022
Project M08031866 Alteration · LOC Issued · 12/27/2022
Project M08031662 Alteration · LOC Issued · 12/23/2022
Project M00227762 Alteration · Permit Entire · 10/15/2019
Project M00227777 Alteration · Permit Entire · 10/15/2019
Project M00227797 Alteration · Permit Entire · 10/15/2019
Project M00194497 Alteration · Permit Entire · 07/26/2019
Project M00198474 Alteration · Permit Entire · 07/26/2019
LFG AmericaOfficeFloor 33
Project M01187912 Alteration · LOC Issued · 03/18/2025
Project M01187923 Alteration · LOC Issued · 03/18/2025
NayaRestaurant / Food ServiceFloor 1
Project M01128003 Alteration · LOC Issued · 01/17/2025
Project M01053707 Alteration · LOC Issued · 06/13/2024
Project M01053735 Alteration · Permit Entire · 06/13/2024
Project M01053839 Alteration · LOC Issued · 06/13/2024
Project M01053656 Alteration · LOC Issued · 06/11/2024
Aperture InvestorsOfficeFloors 30, 34
Project M01149706 Alteration · LOC Issued · 12/05/2024
Project M01149755 Alteration · LOC Issued · 12/05/2024
Project M01149806 Alteration · LOC Issued · 12/04/2024
Project M01149820 Alteration · LOC Issued · 12/04/2024
Project M00657583 Alteration · LOC Issued · 01/28/2022
SpyscapeArts / Culture / EntertainmentFloor 2
Project M01114908 Alteration · LOC Issued · 09/24/2024
Project M00893217 Alteration · LOC Issued · 06/27/2023
LS PowerOfficeFloors 30, 31
Project M01067043 Alteration · Permit Entire · 07/18/2024
Project M01064851 Alteration · LOC Issued · 07/17/2024
Project M01067087 Alteration · Permit Entire · 07/17/2024
Project M01067111 Alteration · Permit Entire · 07/17/2024
Project M01064882 Alteration · LOC Issued · 07/16/2024
McCarter & EnglishOfficeFloor 13
Project M01026357 Alteration · Permit Entire · 04/29/2024
Project M01026375 Alteration · LOC Issued · 04/29/2024
Project M01026389 Alteration · Permit Entire · 04/29/2024
Project M01026334 Alteration · LOC Issued · 04/24/2024
Arnold & PorterOfficeSub-cellar, Floors 2, 5, 9–11, 14
Project M00956936 Alteration · LOC Issued · 11/21/2023
Project M00956970 Alteration · LOC Issued · 11/21/2023
Project M00957018 Alteration · LOC Issued · 11/21/2023
GlazerOfficeFloor 30
Project M08052115 Alteration · Permit Entire · 01/09/2023
Morrison & FoersterOfficeCellar, Floor 22
Project M00685534 Alteration · LOC Issued · 03/17/2022
Project M00631380 Alteration · LOC Issued · 03/16/2022
Project M00681021 Alteration · LOC Issued · 03/16/2022
Project M00685542 Alteration · LOC Issued · 03/16/2022
TD BankBank / Financial branch—
Project M00626567 Alteration · LOC Issued · 11/20/2021
Project M00626834 Alteration · LOC Issued · 11/20/2021
Soros Fund ManagementOfficeFloor 26
Project M00314877 Alteration · LOC Issued · 02/26/2020
Project M00314895 Alteration · Permit Entire · 02/26/2020
Click-fil-aRestaurant / Food ServiceFloor 1
Project M00087788 Alteration · LOC Issued · 10/22/2018
Project M00087790 Alteration · LOC Issued · 10/22/2018
SkyscapeOffice—
Project M00003101 Alteration · LOC Issued · 12/22/2017
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 5,225 on file (BIS + DOB NOW)
▸Plans & Drawings116
▸DOB NOWPlans/Sketch83
09/06/2026M00003101-I1Request digital key ↗
09/06/2026M00087788-I1Request digital key ↗
09/06/2026M00087790-I1Request digital key ↗
Showing 3 of 83 on file for this type
▸DOB NOWPlans/Sketch - Temporary Place of Assembly13
09/06/2026M00112630-I1Request digital key ↗
09/05/2026M00113700-I1Request digital key ↗
09/05/2026M00126347-I1Request digital key ↗
Showing 3 of 13 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler7
09/05/2026M00198474-I1Request digital key ↗
09/05/2026M00227797-I1Request digital key ↗
09/05/2026M00245980-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems7
09/05/2026M00194497-I1Request digital key ↗
09/05/2026M00227762-I1Request digital key ↗
09/05/2026M00245733-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸DOB NOWPlans/Sketch - Plumbing5
09/05/2026M00227777-I1Request digital key ↗
09/05/2026M00314877-I1Request digital key ↗
09/03/2026M00478280-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - General Construction1
09/03/2026M00473666-I1Request digital key ↗
▸Applications & Permits965
▸BISPLAN / WORK APPROVAL APPLICATION580
01/30/2026104870533Open ↗
01/28/2026104870533Open ↗
04/26/2024123894759Open ↗
Showing 3 of 580 on file for this type
▸BISWORK PERMIT APPLICATION360
03/06/2020123855845Open ↗
03/02/2020123524668Open ↗
11/22/2019123748677Open ↗
Showing 3 of 360 on file for this type
▸BISPLACE OF ASSEMBLY23
08/01/2025122952135Open ↗
11/12/2024122952135Open ↗
Showing 2 of 23 on file for this type
▸BISNon-Directive 14 Construction Sign Off Including Sign Applications2
09/13/2019121062125Open ↗
09/13/2019121062134Open ↗
▸Zoning, Tax Lot & Property Records22
▸BISZONING RESOLUTION DETERMINATION18
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 18 on file for this type
▸BISZONING EXHIBIT I: CERTIFICATION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISZoning Diagram (ZD1)2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Seals & Professional Certifications1,601
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION874
03/27/2020123813542Open ↗
03/27/2020123813542Open ↗
03/27/2020123748935Open ↗
Showing 3 of 874 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT211
04/19/2022141008727Open ↗
03/05/2020123855845Open ↗
10/01/2019123748935Open ↗
Showing 3 of 211 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST160
03/05/2020123855845Open ↗
11/25/2019123205717Open ↗
10/01/2019123748935Open ↗
Showing 3 of 160 on file for this type
▸DOB NOWProgress Inspector Seal & Signature126
09/28/2026M01142223-P1Open ↗
09/28/2026M01142223-P1Open ↗
09/25/2026M01064851-P1Open ↗
Showing 3 of 126 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature116
09/06/2026M00003101-I1Open ↗
09/06/2026M00087788-I1Open ↗
09/06/2026M00112630-I1Open ↗
Showing 3 of 116 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature69
09/28/2026M01142223-P1Open ↗
09/28/2026M01142223-P1Open ↗
09/25/2026M01064851-P1Open ↗
Showing 3 of 69 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM35
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 35 on file for this type
▸BISProfessional and Owner Certification (POC3)5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISPC FULL REPORT5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸Trade Schedules & Equipment562
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE166
11/15/2019123205726Open ↗
Showing 1 of 166 on file for this type
▸BISSELF-CERT PLUMBING NOTICE147
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 147 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA82
04/12/2023123434514Open ↗
06/15/2021123404468Open ↗
02/10/2020123434417Open ↗
Showing 3 of 82 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT55
07/02/2021123447975Open ↗
06/28/2021123447975Open ↗
11/25/2019122930301Open ↗
Showing 3 of 55 on file for this type
▸BISEQUIPMENT USE PERMITS50
07/02/2021123447975Open ↗
06/28/2021123447975Open ↗
11/25/2019122930301Open ↗
Showing 3 of 50 on file for this type
▸BISSCHEDULE B - PLUMBING39
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 39 on file for this type
▸BISSPRINKLER INSP REPORT : FP-8514
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 14 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISSIGN HANGER CERTIFICATE2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Environmental & Asbestos28
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE TO PROCEED8
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 8 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISENVIRONMENTAL RESTRICTIONS - OER NOTICE OF SATISFACTION2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Energy Compliance295
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS197
03/27/2020123813542Open ↗
03/27/2020123748935Open ↗
03/27/2020123748935Open ↗
Showing 3 of 197 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS67
03/27/2020123748935Open ↗
10/09/2019122981023Open ↗
09/13/2019123306494Open ↗
Showing 3 of 67 on file for this type
▸BISTR8: Energy Code Progress Inspections21
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 21 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.4
09/02/2026M00681021-I1Open ↗
Showing 1 of 4 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
09/24/2021122891415Open ↗
05/20/2021123447975Open ↗
05/20/2021123447975Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)3
08/21/2023123205744Open ↗
01/20/2022123855845Open ↗
03/04/2021123447975Open ↗
▸Inspections & Test Reports16
▸BISHYDRAULIC FLOW CALCULATIONS6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY6
11/08/2024122952135Open ↗
09/24/2021122891415Open ↗
06/28/2021123447975Open ↗
Showing 3 of 6 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)2
08/21/2023123205744Open ↗
01/20/2022123855845Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Approvals, Objections & Sign-offs411
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST259
08/25/2023123434514Open ↗
08/22/2023123434514Open ↗
01/21/2022123855845Open ↗
Showing 3 of 259 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION66
10/09/2019122981023Open ↗
Showing 1 of 66 on file for this type
▸BISADMINISTRATIVE OBJECTIONS49
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 49 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION20
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 20 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE7
01/30/2026104870533Open ↗
01/28/2026104870533Open ↗
12/03/2019104870533Open ↗
Showing 3 of 7 on file for this type
▸BISSUPERSEDING LETTER6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISFINAL2
08/21/2023123205744Open ↗
01/20/2022123855845Open ↗
▸BISLETTERS - APPROVED FABRICATION CERTIFICATIONS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Cost, Insurance & Ownership530
▸BISCOST AFFIDAVIT526
04/19/2022141008727Open ↗
11/23/2021122891415Open ↗
06/15/2020123152747Open ↗
Showing 3 of 526 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW34
08/21/2023123205744Open ↗
08/21/2023123434514Open ↗
01/20/2022123855845Open ↗
Showing 3 of 4 on file for this type
▸Filing & Intake Forms589
▸BISEFILING COVER SHEET344
03/05/2020123855845Open ↗
10/30/2019123748677Open ↗
10/01/2019123748935Open ↗
Showing 3 of 344 on file for this type
▸BISADDITIONAL INFORMATION139
08/25/2025122952135Open ↗
11/05/2020123447975Open ↗
02/19/2020123670964Open ↗
Showing 3 of 139 on file for this type
▸BISBOROUGH INTAKE FORM96
03/27/2020123813542Open ↗
03/27/2020123748935Open ↗
03/23/2020104870533Open ↗
Showing 3 of 96 on file for this type
▸BISeFiling Job Application Cover Sheet10
04/19/2022141008727Open ↗
Showing 1 of 10 on file for this type
▸Other Documents59
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION44
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 44 on file for this type
▸BISSupporting Document: Fee Exempt13
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 13 on file for this type
▸BISSupporting Document: Fee Deferment2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type