← Back
BuildNYC
Office with commercial, 7-19 stories
345 PARK AVENUE SOUTH
MANHATTAN · Gramercy · BIN 1018102
💬 Discuss this project
1913Year Built
12Stories
O6Building Class
C6-4AZoning
244,157 sfGross Floor Area
23Units
LL97 Covered8 Active Violations 1 unresolved · 7 paperwork only 1 old, status unconfirmed ▸FISP: UNSAFEFDNY Report ↗
Office with commercial, 7-19 stories · Owner of record: 345 Pas Holding · 20,737 sf lot · 11.77 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentLandscapeCivilGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Permit Issued — active, not yet Signed-off
Whole building & multi-floor projects345 Pas Holding, LLC5 filings
RoofCoridea, Helaina +1Under Construction8p · 11 filings · 20 docs
Bulkhead345 Pas Holdings LLC1p · 1 filing · 6 docs
PenthouseDeerfield15p · 14 filings · 20 docs
Floor 13Deerfield2p · 2 filings · 20 docs
Floor 12Deerfield10p · 13 filings · 20 docs
Floor 11Deerfield9p · 9 filings · 20 docs
Floor 10Deerfield2p · 4 filings · 10 docs
Floor 9NYU Langone Health, NYU Labs +227p · 14 filings · 20 docs
Floor 8NYU Langone Health, NYU Labs +118p · 7 filings · 20 docs
Floor 7NYU Labs1p · 1 filing · 20 docs
Floor 6Lexeo Millipore, Apertura20p · 15 filings · 20 docs
Floor 5Deerfield, HelainaUnder Construction20p · 6 filings · 20 docs
Floor 4Advancium - Frankel Labs16p · 8 filings · 20 docs
Floor 3Coridea12p · 8 filings · 20 docs
Floor 2Deerfield, CorideaUnder Construction26p · 11 filings · 20 docs
Floor 1Deerfield, Bank of AmericaUnder Construction13p · 12 filings · 20 docs
Cellar345 Pas Holdings LLC4p · 3 filings · 16 docs
Site & exterior345 Pas Holdings LLCUnder Construction16 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
345 Pas Holding54610/13/2026
345 Park Avenue South Partners26803/21/2026
345 Pas Owner9307/08/2026
345 Pas Holding LLC C Odeerfield2703/21/2026
RFR Realty2003/22/2026
Montrose Realty Corp As Agents303/21/2026
Upland Development203/21/2026
Staples103/21/2026
Manzanilla103/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
09/05/2019$344.5M—— → —$1,411/sf building
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Metropolis Group31603/21/2026
Direct Access Expediting1603/21/2026
Green Studio2803/21/2026
Rigid Structural Design2003/21/2026
Building Brothers603/21/2026
Lewsan Consulting803/21/2026
Project Expediters403/21/2026
Outsource Consultants203/21/2026
JP Expedite403/21/2026
Patuxent Engineering403/21/2026
Riggining Consultants103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
L&K PartnersGeneral Contractor4307/08/2026
Newgrange Construction CoGeneral Contractor2909/10/2026
Full Capacity FireFire Protection1407/08/2026
Nova Construction ServiceScaffold1407/08/2026
King Hoist & ScaffoldingScaffold1307/08/2026
Rock Group NYScaffold1307/08/2026
Accurate MechanicalFire Protection907/08/2026
Northeast Plumbing & HeatingPlumbing707/08/2026
Pace PlumbingPlumbing607/08/2026
Platinum Services NYScaffold507/08/2026
Urban IntelligenceScaffold508/13/2026
Nova Construction ServiceGeneral Contractor407/08/2026
Par Plumbing CoPlumbing307/08/2026
Elemco Testing Co Inc DbaElectrical303/21/2026
Going Sign & Servicing CoSign hanger307/08/2026
Variant ServicesGeneral Contractor303/21/2026
William C. Gerakaris P&HPlumbing207/08/2026
Avalon ElectricElectrical203/22/2026
Unity Construction GroupGeneral Contractor207/08/2026
Exterior Wall & BuildingScaffold207/08/2026
L&K PartnersScaffold203/21/2026
Signs CadSign hanger207/08/2026
Systems 2000 Plumbing ServicesPlumbing207/08/2026
A.S.K. ElectricalElectrical203/22/2026
RX ElectricElectrical103/22/2026
S & D Electrical/MechanicalElectrical103/21/2026
Allstate ElectricElectrical103/21/2026
Ami and AssociatesFire Protection107/08/2026
P.L. Electrical ContractingElectrical103/21/2026
Metro Fire ProtectionFire Protection107/08/2026
Commercial Electric ContElectrical103/21/2026
Lintech ElectricElectrical103/22/2026
Penguin Maintenance & ServicesGeneral Contractor107/08/2026
Abco-Peerless SprinklerFire Protection103/21/2026
T. Dirusso Electrical ContElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Jaros, Baum & Bolles1092309/04/2026
Asda Architecture + Desig2015108/28/2026
MEP Inspections11029608/28/2026
Urban Integrations7993307/08/2026
Metric Consulting and Ins1803711/14/2024
CFS Engineering61511910/22/2024
Alan Margolin & Associates423108/12/2024
Becker Engineering633401/25/2022
Building Lifecycle
All (300)Filed (79)Permit Issued (69)Signed Off (24)Facade (FISP) (9)Violation (39)Inspection (46)Objection (4)Special Inspection (30)
10/19/2026
Signed off — Alteration
Installation of a temporarily shanty per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01155156-I1
09/14/2026
Filed — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01145443-P4
09/09/2026
Permit issued — Mechanical Systems
M01415584-S1-MS
09/09/2026
Permit issued — General Construction
M01415584-I1-GC
09/04/2026
Filed — Alteration
HEREWITH FILING FOR SPRINKLER MODIFICATION WORK AS PER PLANS
M01415584-S1
09/01/2026
Filed — Alteration
HEREWITH FILING FOR SPRINKLER MODIFICATION WORK AS PER PLANS
M01415584-S3
09/01/2026
Filed — Alteration
HEREWITH FILING FOR SPRINKLER MODIFICATION WORK AS PER PLANS
M01415584-S2
08/28/2026
Filed — Alteration
HEREWITH FILING FOR SPRINKLER MODIFICATION WORK AS PER PLANS
M01415584-I1
08/19/2026
Special inspection requirement — Post-installed Anchors
Nicolas Crosetto
08/19/2026
Special inspection requirement — Fire-Resistance Rated Construction
Alfonso DElia
08/12/2026
Permit issued — Sidewalk Shed
M01022418-I1-SH
08/11/2026
Cycle 9 facade report submitted
08/11/2026
Cycle 9 facade report signed — UNSAFE
08/03/2026
Special inspection requirement — Post-installed Anchors
DANNY TRUJILLO
08/03/2026
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Amal Hassan Hassan
08/03/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
DANNY TRUJILLO
07/31/2026
Cycle 9 facade inspection completed
07/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Alfonso DElia
07/30/2026
Special inspection requirement — Post-installed Anchors
RYAN LEAN
07/30/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
RYAN LEAN
07/30/2026
Special inspection requirement — HVAC-R and service water heating equipment
RYAN LEAN
07/30/2026
Special inspection requirement — Energy Code Compliance Inspections
RYAN LEAN
07/30/2026
Special inspection requirement — HVAC-R and service water heating system controls
RYAN LEAN
07/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
RYAN LEAN
07/30/2026
Special inspection requirement — Post-installed Anchors
RYAN LEAN
07/30/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
RYAN LEAN
07/28/2026
Special inspection requirement — HVAC-R and service water heating system controls
RYAN LEAN
07/28/2026
Special inspection requirement — Metering
RYAN LEAN
07/28/2026
Special inspection requirement — Duct leakage testing, insulation and design
RYAN LEAN
07/28/2026
Special inspection requirement — Interior lighting power
RYAN LEAN
07/28/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
RYAN LEAN
07/28/2026
Special inspection requirement — Maintenance information
RYAN LEAN
07/28/2026
Special inspection requirement — Lighting controls
RYAN LEAN
07/28/2026
Special inspection requirement — Energy Code Compliance Inspections
RYAN LEAN
07/15/2026
Filed — Alteration
Installation of a temporarily supported scaffold per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01145443-P3
07/08/2026
Filed — Alteration
Installation of a suspended scaffold for Facade Inspection and repair as per plan submitted. No change to egress or occupancy.
M01153239-P2
07/08/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
DANNY TRUJILLO
07/08/2026
Special inspection requirement — Alternative Materials - OTCR Buildings Bulletin Number
Amal Hassan Hassan
07/08/2026
Special inspection requirement — Post-installed Anchors
DANNY TRUJILLO
07/07/2026
Violation issued (ECB, open)
Unknown
07/07/2026
Violation issued (ECB, open)
Construction
07/07/2026
Violation issued (ECB, open)
Site Safety
07/07/2026
Violation issued (ECB, open)
Cranes and Derricks
07/07/2026
Violation issued (ECB, open)
Construction
07/07/2026
Violation issued (ECB, open)
Cranes and Derricks
07/01/2026
Special inspection requirement — Final
RYAN LEAN
07/01/2026
Special inspection requirement — Sprinkler Systems
RYAN LEAN
07/01/2026
Special inspection requirement — Mechanical Systems
RYAN LEAN
06/11/2026
Special inspection requirement — Final
Alfonso DElia
05/20/2026
Permit issued — Sidewalk Shed
M01022418-I1-SH
04/23/2026
Signed off — Alteration
M01193033-I1
04/23/2026
Signed off — Alteration
HEREWITH FILING FOR DEERFIELD TENANT FITOUT WORK. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M00907102-I1
04/20/2026
Permit issued — General Construction
M01306701-I1-GC
04/14/2026
Permit issued — Protection and Mechanical Methods
M01176967-I1-PMM
04/01/2026
Filed — Alteration
Installation of a temporary roof protection per plan submitted. Work shall comply with 2022 building codes chapter 33. No change in use, egress and/or occupancy with this application.
M01176967-P1
03/04/2026
Violation issued (FDNY_NOV, closed)
02/10/2026
Signed off — Alteration
HEREWITH FILING FOR PLUMBING WORK AS PER PLANS.
M00938830-I1
02/09/2026
Permit issued — Suspended Scaffold
M01153239-I1-SC
02/06/2026
Filed — Alteration
HEREWITH FILING FOR MINOR INTERIOR GENERAL CONSTRUCTION WORK AS PER PLANS. NO CHANGE TO USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
M01351933-I1
01/27/2026
Special inspection requirement — Final
Nicolas Crosetto
Latest 60 of 300 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedNewgrange Construction Co09/09/2026
DOB NOWMechanical SystemsPermit IssuedNewgrange Construction Co09/09/2026
DOB NOWSidewalk ShedPermit IssuedUrban Intelligence08/12/2026
DOB NOWSidewalk ShedPermit IssuedUrban Intelligence05/20/2026
DOB NOWGeneral ConstructionPermit IssuedNewgrange Construction Co04/20/2026
DOB NOWProtection and Mechanical MethodsPermit IssuedNova Construction Service04/14/2026
DOB NOWSuspended ScaffoldPermit IssuedNova Restoration02/09/2026
DOB NOWSidewalk ShedPermit IssuedExterior Wall & Building12/30/2025
DOB NOWProtection and Mechanical MethodsPermit IssuedNova Construction Service12/22/2025
DOB NOWProtection and Mechanical MethodsSigned-offNova Construction Service12/22/2025
DOB NOWProtection and Mechanical MethodsPermit IssuedNova Construction Service12/22/2025
DOB NOWGeneral ConstructionPermit IssuedNova Construction Service12/22/2025
DOB NOWSupported ScaffoldPermit IssuedNova Construction Service11/18/2025
DOB NOWMechanical SystemsSigned-offUnity Construction Group08/18/2025
DOB NOWSprinklersSigned-offAmi and Associates08/18/2025
DOB NOWGeneral ConstructionPermit IssuedUnity Construction Group08/15/2025
DOB NOWProtection and Mechanical MethodsPermit IssuedNova Construction Service04/28/2025
DOB NOWGeneral ConstructionSigned-offNewgrange Construction Co04/02/2025
DOB NOWMechanical SystemsSigned-offNewgrange Construction Co03/25/2025
DOB NOWSuspended ScaffoldPermit IssuedNova Restoration02/10/2025
DOB NOWProtection and Mechanical MethodsSigned-offNova Construction Service02/03/2025
DOB NOWProtection and Mechanical MethodsPermit IssuedNova Construction Service01/24/2025
DOB NOWProtection and Mechanical MethodsPermit IssuedNova Construction Service01/23/2025
DOB NOWGeneral ConstructionPermit IssuedNova Construction Service01/21/2025
DOB NOWGeneral ConstructionPermit IssuedL&K Partners01/08/2025
DOB NOWSidewalk ShedPermit IssuedExterior Wall & Building12/27/2024
DOB NOWSupported ScaffoldPermit IssuedNova Construction Service11/27/2024
DOB NOWCurb CutPermit IssuedNewgrange Construction Co09/12/2024
DOB NOWSprinklersPermit IssuedFull Capacity Fire08/13/2024
DOB NOWMechanical SystemsPermit IssuedNewgrange Construction Co05/28/2024
DOB NOWGeneral ConstructionSigned-offL&K Partners04/19/2024
DOB NOWMechanical SystemsPermit IssuedPenguin Maintenance & Services04/16/2024
DOB NOWSidewalk ShedPermit IssuedUrban Intelligence03/25/2024
DOB NOWMechanical SystemsPermit IssuedNewgrange Construction Co03/15/2024
DOB NOWPlumbingSigned-offPar Plumbing Co02/27/2024
DOB NOWSuspended ScaffoldSigned-offStructural Preservation System01/10/2024
DOB NOWGeneral ConstructionPermit IssuedNewgrange Construction Co10/18/2023
DOB NOWPlumbingSigned-offPace Plumbing06/29/2023
DOB NOWMechanical SystemsSigned-offNewgrange Construction Co04/17/2023
DOB NOWGeneral ConstructionSigned-offNewgrange Construction Co04/11/2023
+ 60 more permits on file
7 projects · most recent 09/04/2026
Air Conditioning Systems Associated Ducts and Piping Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
09/04/2026Permit IssuedNewgrange Construction CoAir Conditioning Systems, Ventilation Systems
Cooling
Liebert DME044C 130,680 BTU · Crac Unit ×2
Ventilation
Iec HTY20 1,860 CFM ×6
HTY16 1,540 CFM ×3
HTY10 620 CFM ×2
HTY08 540 CFM · Wshp ×1
HTY18 1,650 CFM ×1
10/22/2024——Air Conditioning Systems
Cooling
Liebert DME044C 15 BTU · Crac Unit ×1
08/12/2024Signed-offNewgrange Construction CoAir Conditioning Systems
Cooling
Stulz OHS-018 8,642 BTU · Packaged Unit ×1
OHS-040 14,625 BTU · Packaged Unit ×1
Vertiv Evaporator Model Number: MT036HE1P0, Condensing Unit Model Number: MTC38WDP21 39,700 BTU ×1
Evaporator Model: MT036HE1P0, Condensing Unit Model: MTC38WDP21 39,700 BTU · Crac Unit ×1
07/02/2024——Associated Ducts and Piping
Ducts & Piping
02/15/2024Permit IssuedNewgrange Construction CoAir Conditioning Systems, Associated Ducts and Piping
Cooling
Liebert MMD20W 21 BTU · Crac Unit ×6
MTC38W 40 BTU · Crac Unit ×4
DME037E 35 BTU · Crac Unit ×2
Iec HDY30 89,925 BTU · Fan Coil Indoor ×2
Ducts & Piping
12/20/2023——Associated Ducts and Piping
Ducts & Piping
12/14/2023Permit IssuedNewgrange Construction CoAir Conditioning Systems, Associated Ducts and Piping
Cooling
Iec HDY30 118,232 BTU · Fan Coil Indoor ×1
HPY12 14,722 BTU · Fan Coil Indoor ×1
Liebert DME020E 17 kW · Crac Unit ×1
MTC38W 40 kW · Crac Unit ×1
4 projects · most recent 09/04/2026
Sprinkler System
FiledStatusContractorScope
09/04/2026——104 heads
08/15/2025Signed-offAmi and AssociatesSprinkler System
12/20/2023Permit IssuedFull Capacity Fire—
02/11/2023——184 heads, 1 outlets
2 projects · most recent 09/04/2026
Water/Sanitary
FiledStatusContractorScope
09/04/2026——Water/Sanitary
08/15/2025———
25 projects · most recent 05/14/2025
General Wiring
FiledStatusContractorScope
05/14/2025Permit IssuedAvalon Electric—
05/07/2025CompleteAvalon ElectricGeneral Wiring
07/18/2024Permit IssuedRX ElectricGeneral Wiring
03/26/2024Permit Issued5 J'S Electl Conts—
06/28/2023CompleteA.S.K. ElectricalGeneral Wiring
01/31/2023Permit IssuedA.S.K. ElectricalGeneral Wiring
11/28/2022Permit IssuedRX ElectricGeneral Wiring
11/28/2022CompleteRX Electric—
03/08/2022CompleteRX ElectricGeneral Wiring
10/18/2021Permit IssuedNee Electrical—
10/11/2021Permit IssuedRX ElectricGeneral Wiring
10/11/2021Permit IssuedRX Electric—
10/01/2021CompleteA.S.K. ElectricalGeneral Wiring
09/24/2021CompleteA.S.K. ElectricalGeneral Wiring
08/24/2021CompleteT. Dirusso Electrical ContGeneral Wiring
6 projects · most recent 09/14/2026
Scaffold Sidewalk Shed
FiledStatusContractorScope
09/14/2026Permit IssuedNova Construction ServiceScaffold
10/13/2025Permit IssuedUrban IntelligenceSidewalk Shed
03/16/2021Permit IssuedKing Hoist & ScaffoldingScaffold
12/04/2020Permit IssuedKing Hoist & ScaffoldingScaffold
02/19/2020Permit IssuedKing Hoist & ScaffoldingSidewalk Shed
05/16/2019Permit IssuedKing Hoist & ScaffoldingScaffold
1 project · most recent 07/08/2026
Suspended Scaffold (SC)
FiledStatusContractorScope
07/08/2026Permit IssuedNova RestorationSuspended Scaffold (SC)
▾Field Inspections (DOB CAP) — 58
DateTypeResultReport
09/09/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/05/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
01/16/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
01/13/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
03/11/2024Pass-Final Boiler Equipment InspectionPassView ↗
03/07/2024No Access-Final Boiler Equipment InspectionNo AccessView ↗
10/13/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
10/12/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
09/28/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/25/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
09/13/2023Certified Medical Gas - MG - PL - FinishCertifiedView ↗
09/13/2023Certified Medical Gas - MG - PL - RoughingCertifiedView ↗
09/13/2023Certified Medical Gas - MG - PL - TestCertifiedView ↗
09/12/2023Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
09/11/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/07/2023Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
09/07/2023Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
09/07/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/09/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
05/01/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/28/2023Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
04/27/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
02/28/2023Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
01/24/2023Certified Medical Gas - MG - PL - FinishCertifiedView ↗
01/24/2023Certified Medical Gas - MG - PL - RoughingCertifiedView ↗
Latest 25 of 58.
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
08/19/2026Fire-Resistance Rated ConstructionAlfonso DEliaprogress
08/19/2026Post-installed AnchorsNicolas Crosettospecial
08/03/2026Alternative Materials - OTCR Buildings Bulletin NumberAmal Hassan Hassanspecial
08/03/2026Structural Stability – Alterations of existing buildingsDANNY TRUJILLOspecial
08/03/2026Post-installed AnchorsDANNY TRUJILLOspecial
07/30/2026Post-installed AnchorsRYAN LEANspecial
07/30/2026HVAC-R and service water piping design and insulationRYAN LEANenergy_progress
07/30/2026HVAC-R and service water heating equipmentRYAN LEANenergy_progress
07/30/2026Energy Code Compliance InspectionsRYAN LEANprogress
07/30/2026Fire-Resistant Penetrations and JointsAlfonso DEliaspecial
07/30/2026Post-installed AnchorsRYAN LEANspecial
07/30/2026HVAC-R and service water heating system controlsRYAN LEANenergy_progress
07/30/2026Fire-Resistant Penetrations and JointsRYAN LEANspecial
07/30/2026Fire-Resistant Penetrations and JointsRYAN LEANspecial
07/28/2026Maintenance informationRYAN LEANenergy_progress
07/28/2026Lighting controlsRYAN LEANenergy_progress
07/28/2026Interior lighting powerRYAN LEANenergy_progress
07/28/2026HVAC-R and service water piping design and insulationRYAN LEANenergy_progress
07/28/2026MeteringRYAN LEANenergy_progress
07/28/2026HVAC-R and service water heating system controlsRYAN LEANenergy_progress
07/28/2026Duct leakage testing, insulation and designRYAN LEANenergy_progress
07/28/2026Energy Code Compliance InspectionsRYAN LEANprogress
07/08/2026Post-installed AnchorsDANNY TRUJILLOspecial
07/08/2026Alternative Materials - OTCR Buildings Bulletin NumberAmal Hassan Hassanspecial
07/08/2026Structural Stability – Alterations of existing buildingsDANNY TRUJILLOspecial
Latest 25 of 150.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
DeerfieldOfficeFloors 1, 2, 5, 8–12, Penthouse, Roof
Project M01415584 Alteration · Permit Entire · 08/28/2026
Project M01351933 Alteration · Approved · 02/06/2026
Project M01306701 Alteration · Permit Entire · 11/04/2025
Project M01253879 Alteration · Permit Entire · 08/07/2025
Project M00907104 Alteration · Permit Entire · 12/20/2023
Project M00938830 Alteration · LOC Issued · 10/17/2023
Project M00938833 Alteration · Filing Withdrawn · 10/17/2023
Project M00938835 Alteration · Filing Withdrawn · 10/17/2023
Project M00938828 Alteration · Permit Entire · 10/16/2023
Project M00907103 Alteration · Approved · 08/28/2023
Project M00907102 Alteration · LOC Issued · 08/15/2023
Project M00623342 Alteration · LOC Issued · 11/12/2021
Advancium - Frankel LabsLaboratoryFloor 4
Project M01083693 Alteration · Approved · 10/24/2024
Project M01083691 Alteration · Permit Entire · 10/22/2024
Project M01083692 Alteration · Approved · 10/22/2024
Project M00968265 Alteration · Permit Entire · 12/14/2023
Project M08023549 Alteration · LOC Issued · 11/03/2022
Project M08023550 Alteration · LOC Issued · 11/03/2022
Project M08023551 Alteration · LOC Issued · 11/03/2022
Project M08023552 Alteration · LOC Issued · 11/03/2022
NYU Langone HealthMedical / HealthcareFloors 8, 9
Project M01081844 Alteration · Permit Entire · 08/12/2024
HelainaOfficeFloor 5
Project M01015749 Alteration · Permit Entire · 03/08/2024
Project M00574689 Alteration · LOC Issued · 09/22/2021
Project M00574055 Alteration · LOC Issued · 09/17/2021
Project M00574060 Alteration · LOC Issued · 09/17/2021
Project M00574705 Alteration · LOC Issued · 09/17/2021
NYU LabsLaboratoryFloors 7–9
Project M00968266 Alteration · Permit Entire · 12/14/2023
Project M08006646 Alteration · LOC Issued · 10/11/2022
Project M08006645 Alteration · LOC Issued · 10/06/2022
Project M08006643 Alteration · LOC Issued · 09/29/2022
Project M08006644 Alteration · LOC Issued · 09/29/2022
AperturaLaboratoryFloor 6
Project M00834571 Alteration · LOC Issued · 03/28/2023
Project M00834572 Alteration · LOC Issued · 03/28/2023
Project M00733800 Alteration · LOC Issued · 06/16/2022
Project M00733813 Alteration · LOC Issued · 06/16/2022
Project M00733782 Alteration · LOC Issued · 06/08/2022
Project M00733795 Alteration · LOC Issued · 06/08/2022
Lexeo MilliporeLaboratoryFloor 6
Project M00705320 Alteration · LOC Issued · 05/06/2022
Project M00705329 Alteration · LOC Issued · 05/06/2022
Project M00728874 Alteration · LOC Issued · 05/04/2022
Project M00705323 Alteration · LOC Issued · 05/03/2022
Project M00705326 Alteration · LOC Issued · 05/03/2022
Addison PHSOfficeFloor 9
Project M00580148 Alteration · LOC Issued · 08/31/2021
CorideaOfficeFloors 2, 3, Roof
Project M00555315 Alteration · LOC Issued · 08/02/2021
Project M00558000 Alteration · LOC Issued · 07/30/2021
Project M00558003 Alteration · LOC Issued · 07/30/2021
Project M00558491 Alteration · LOC Issued · 07/30/2021
Project M00554507 Alteration · LOC Issued · 07/29/2021
Bank of AmericaBank / Financial branchFloor 1
Project M00450256 Alteration · LOC Issued · 03/29/2021
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 3,234 on file (BIS + DOB NOW)
▸Plans & Drawings221
▸DOB NOWPlans/Sketch139
09/15/2026M01415584-I1Request digital key ↗
09/15/2026M01415584-S1Request digital key ↗
09/15/2026M01415584-S3Request digital key ↗
Showing 3 of 139 on file for this type
▸DOB NOWPlans/Sketch - Sprinkler16
09/04/2026M00403300-I1Request digital key ↗
09/04/2026M00337274-I1Request digital key ↗
09/04/2026M00337274-P1Request digital key ↗
Showing 3 of 16 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold12
09/05/2026M00335848-I1Request digital key ↗
09/05/2026M00335848-P6Request digital key ↗
09/04/2026M00377588-I1Request digital key ↗
Showing 3 of 12 on file for this type
▸DOB NOWPlans/Sketch - Sidewalk Shed10
09/06/2026M00051307-P7Request digital key ↗
09/06/2026M00051307-I1Request digital key ↗
09/06/2026M00051307-P1Request digital key ↗
Showing 3 of 10 on file for this type
▸DOB NOWPlans/Sketch - Plumbing10
09/05/2026M00280114-I1Request digital key ↗
09/05/2026M00345869-I1Request digital key ↗
09/04/2026M00403297-I1Request digital key ↗
Showing 3 of 10 on file for this type
▸DOB NOWPlans/Sketch - Standpipe8
09/04/2026M00373709-I1Request digital key ↗
09/04/2026M00373709-P1Request digital key ↗
09/04/2026M00337274-I1Request digital key ↗
Showing 3 of 8 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems6
09/05/2026M00345860-I1Request digital key ↗
09/04/2026M00432659-P1Request digital key ↗
09/04/2026M00432659-I1Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Construction Fence5
09/05/2026M00135839-I1Request digital key ↗
09/04/2026M00390662-P1Request digital key ↗
09/04/2026M00390662-I1Request digital key ↗
Showing 3 of 5 on file for this type
▸DOB NOWPlans/Sketch - Temporary Place of Assembly5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸DOB NOWPlans/Sketch - General Construction2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸DOB NOWPlans/Sketch - Boiler Equipment2
09/04/2026M00419440-P1Request digital key ↗
Showing 1 of 2 on file for this type
▸Applications & Permits457
▸BISPLAN / WORK APPROVAL APPLICATION280
11/13/2023123385899Open ↗
11/09/2023123385899Open ↗
06/29/2023123385899Open ↗
Showing 3 of 280 on file for this type
▸BISWORK PERMIT APPLICATION173
01/06/2023123385899Open ↗
Showing 1 of 173 on file for this type
▸BISPLACE OF ASSEMBLY3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Seals & Professional Certifications1,024
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION251
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 251 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature221
09/10/2026M01415584-S3Open ↗
09/10/2026M01415584-S2Open ↗
09/10/2026M01415584-S1Open ↗
Showing 3 of 221 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature200
10/19/2026M00558000-P1Open ↗
10/19/2026M00558000-P1Open ↗
10/03/2026M00705323-I1Open ↗
Showing 3 of 200 on file for this type
▸DOB NOWProgress Inspector Seal & Signature172
10/03/2026M00705323-I1Open ↗
10/03/2026M00705323-I1Open ↗
10/03/2026M00705320-P1Open ↗
Showing 3 of 172 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST69
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 69 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT58
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 58 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM25
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 25 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY10
05/12/2023141023023Open ↗
Showing 1 of 10 on file for this type
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸BISPC FULL REPORT9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸Trade Schedules & Equipment253
▸BISEQUIPMENT USE PERMITS69
05/19/2023123385899Open ↗
05/19/2023123385899Open ↗
05/19/2023123385899Open ↗
Showing 3 of 69 on file for this type
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE58
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 58 on file for this type
▸BISSELF-CERT PLUMBING NOTICE44
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 44 on file for this type
▸BISSCHEDULE B - PLUMBING40
12/15/2021123779580Open ↗
12/14/2021123684101Open ↗
12/14/2021123779599Open ↗
Showing 3 of 40 on file for this type
▸BISFA - FDNY APPROVAL : FD-FAA18
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 18 on file for this type
▸BISEQUIPMENT USE APPLICATION/PERMIT14
05/19/2023123385899Open ↗
05/19/2023123385899Open ↗
05/19/2023123385899Open ↗
Showing 3 of 14 on file for this type
▸BISSPRINKLER SYSTEMS5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISSTANDPIPE SYSTEMS4
01/10/2022123779580Open ↗
01/10/2022123779606Open ↗
01/10/2022123779599Open ↗
Showing 3 of 4 on file for this type
▸BISSCHEDULE C - HEATING & COMBUSTION EQUIPMENT1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Safety & Tenant Protection11
▸DOB NOWTenant Protection Plan4
09/06/2026M00051307-P7Open ↗
09/06/2026M00051307-P8Open ↗
09/06/2026M00051307-P6Open ↗
Showing 3 of 4 on file for this type
▸BISDEMOLITION SUBMITTAL CERTIFICATION FORM2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISSTREET TREE SUPPORTING DOCUMENT2
06/02/2023141023023Open ↗
06/02/2023141023023Open ↗
▸BISSTREET TREE CHECKLIST2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸BISTenant Protection Plan and Notes1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Environmental & Asbestos263
▸DOB NOWDEP ACP-5: Asbestos Assessment Report153
09/10/2026M01415584-S3Open ↗
09/10/2026M01415584-S1Open ↗
09/10/2026M01415584-S2Open ↗
Showing 3 of 153 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)69
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 69 on file for this type
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'35
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 35 on file for this type
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type
▸Energy Compliance120
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS47
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 47 on file for this type
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY21
10/26/2021140987252Open ↗
Showing 1 of 21 on file for this type
▸BISAS-BUILT ENERGY ANALYSIS20
11/23/2021140987252Open ↗
09/08/2021140970590Open ↗
Showing 2 of 20 on file for this type
▸DOB NOWEN2: As Built Energy Analysis.11
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 11 on file for this type
▸BISTR8: Energy Code Progress Inspections10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISTECHNICAL REPORT: ENERGY5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸Inspections & Test Reports90
▸BISTECHNICAL REPORT: RESPONSIBILITY68
01/03/2022123684101Open ↗
01/03/2022123779599Open ↗
01/03/2022123779580Open ↗
Showing 3 of 68 on file for this type
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER10
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 10 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX7
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 7 on file for this type
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)5
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 5 on file for this type
▸Approvals, Objections & Sign-offs225
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST110
01/12/2022123684101Open ↗
01/11/2022123779599Open ↗
01/11/2022123779580Open ↗
Showing 3 of 110 on file for this type
▸BISADMINISTRATIVE OBJECTIONS43
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 43 on file for this type
▸BISSCHEDULE A - OCCUPANCY / USE26
11/13/2023123385899Open ↗
11/09/2023123385899Open ↗
06/29/2023123385899Open ↗
Showing 3 of 26 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter22
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 22 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION13
01/06/2023123385899Open ↗
Showing 1 of 13 on file for this type
▸BISSUPERSEDING LETTER6
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISCONSTRUCTION CODE DETERMINATION3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸BISLETTERS - APPROVED FABRICATION CERTIFICATIONS2
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 2 on file for this type
▸Cost, Insurance & Ownership180
▸BISCOST AFFIDAVIT174
01/04/2022123684101Open ↗
01/04/2022123779599Open ↗
01/04/2022123779606Open ↗
Showing 3 of 174 on file for this type
▸BISCOST AFFIDAVIT (FINAL): PW34
01/10/2022123779606Open ↗
01/10/2022123779580Open ↗
01/10/2022123684101Open ↗
Showing 3 of 4 on file for this type
▸BISOK TO ISSUE TCO PENDING RESOLUTION OFOPEN FACADE VIOLATION - AFFIDAVIT ATTACHED2
05/21/2025123385899Open ↗
12/12/2024123385899Open ↗
▸Filing & Intake Forms289
▸BISEFILING COVER SHEET119
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 119 on file for this type
▸BISBOROUGH INTAKE FORM83
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 83 on file for this type
▸BISADDITIONAL INFORMATION74
11/16/2023123385899Open ↗
06/02/2023141023023Open ↗
04/13/2023123385899Open ↗
Showing 3 of 74 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET13
05/12/2023141023023Open ↗
Showing 1 of 13 on file for this type
▸Other Documents76
▸DOB NOWProof of Historic Building39
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 39 on file for this type
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION9
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 9 on file for this type
▸DOB NOWAlternate Plan 16
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸DOB NOWAlternate Plan 26
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 6 on file for this type
▸BISTCO - Supporting Documents4
12/23/2025123385899Open ↗
03/30/2022123385899Open ↗
Showing 2 of 4 on file for this type
▸BISPlot Diagram4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWCalculations4
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 4 on file for this type
▸DOB NOWManufacturer's Specifications3
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 3 on file for this type
▸DOB NOWIRA Certification1
On file, but not among the 200 most recently loaded documents for this source.
Showing 0 of 1 on file for this type