| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| B01350140 ↗ | 151 COURT STREET BROOKLYN | Alteration | Filed — no permit on record | 08/14/2026 | — | Design EK ENGINEERING,P.C. Filer S&M EXPEDITING | — |
| B01383764 ↗ | 151 COURT STREET BROOKLYN | Alteration | Permit Issued | 06/08/2026 | 08/11/2026 | Design EK ENGINEERING,P.C. Contractor FOUR STAR AIR CON'D CO LL Filer S&M EXPEDITING | Installation of Air-Source Heat pump units for apartments as shown on submitted plans. No change in occupancy, use or egress. |
| M01342756 ↗ | 2459 FREDRICK DOUGLASS BL MANHATTAN | Alteration | Permit Issued | 01/07/2026 | 06/26/2026 | Design EK ENGINEERING,P.C. Owner Gibbons Realty Corp Contractor EXPERT FIRE SPRINKLER LLC Filer R CONSULTING | We respectfully wish to file mechanical work on the first floor as per plans. New duct work, new air conditioning units as per plans. |
| X00931637 ↗ | 441 EAST 164 STREET BRONX | Alteration | Filed — no permit on record | 01/10/2024 | — | Design EK ENGINEERING,P.C. Owner SHLEPPERS HOLDINGS LLC | — |
| X00944875 ↗ | 434 EAST 165 STREET BRONX | Alteration | Filed — no permit on record | 01/10/2024 | — | Design EK ENGINEERING,P.C. Owner SHLEPPERS HOLDINGS LLC | — |
| X00961633 ↗ | 315 CASANOVA STREET BRONX | Alteration | Signed-off | 12/22/2023 | 01/04/2024 | Design EK ENGINEERING,P.C. Contractor TAINO MECHANICAL CONTRACT | DESIGN FOR THE REPLACEMENT OF TWO ROOF TOP AC UNITS FOR THE BUILDING AS SHOWN ON PLANS. THERE IS NO CHANGE IN USE, OCCUPANCY OR MEANS OF EGR… |
| Name | Projects together | Most recent |
|---|---|---|
| EK ENGINEERING,P.C. | 15 | 08/14/2026 |
| MARK VETTER ARCHITECTURE | 1 | 02/24/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| AIDEN HVAC MECHANICAL INC | 1 | 06/12/2021 |
| ARROW CONSTRUCTION CONSUL | 1 | 02/24/2022 |
| CONTINENTAL NETWORK CORP | 1 | 10/20/2022 |
| EXPERT FIRE SPRINKLER LLC | 1 | 01/07/2026 |
| FOUR STAR AIR CON'D CO LL | 1 | 06/08/2026 |
| KYPROS MECHANICAL CORP | 1 | 07/28/2021 |
| LOVE YOUR HOME CONTRACTIN | 1 | 08/08/2021 |
| NICHOLAS A. CANTATORE | 1 | 12/01/2022 |
| RIGHT TEMP MECHANICAL INC | 1 | 03/01/2021 |
| TAINO MECHANICAL CONTRACT | 1 | 12/22/2023 |
| WAXTEL LLC | 1 | 10/31/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| ARISTA REAL ESTATE HOLDINGS | 2 | 08/14/2026 |
| JEMCAP | 2 | 10/31/2022 |
| SHLEPPERS HOLDINGS LLC | 2 | 01/10/2024 |
| EQUITY RESIDENTIAL | 1 | 10/28/2019 |
| Gibbons Realty Corp | 1 | 01/07/2026 |
| Name | Projects together | Most recent |
|---|---|---|
| S&M EXPEDITING | 7 | 08/14/2026 |
| R CONSULTING | 1 | 01/07/2026 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| B01350140 ↗ | 151 COURT STREET BROOKLYN | Alteration | Filed — no permit on record | 08/14/2026 | — | Design EK ENGINEERING,P.C. Filer S&M EXPEDITING | — |
| B01383764 ↗ | 151 COURT STREET BROOKLYN | Alteration | Permit Issued | 06/08/2026 | 08/11/2026 | Design EK ENGINEERING,P.C. Contractor FOUR STAR AIR CON'D CO LL Filer S&M EXPEDITING | Installation of Air-Source Heat pump units for apartments as shown on submitted plans. No change in occupancy, use or egress. |
| M01342756 ↗ | 2459 FREDRICK DOUGLASS BL MANHATTAN | Alteration | Permit Issued | 01/07/2026 | 06/26/2026 | Design EK ENGINEERING,P.C. Owner Gibbons Realty Corp Contractor EXPERT FIRE SPRINKLER LLC Filer R CONSULTING | We respectfully wish to file mechanical work on the first floor as per plans. New duct work, new air conditioning units as per plans. |
| X00931637 ↗ | 441 EAST 164 STREET BRONX | Alteration | Filed — no permit on record | 01/10/2024 | — | Design EK ENGINEERING,P.C. Owner SHLEPPERS HOLDINGS LLC | — |
| X00944875 ↗ | 434 EAST 165 STREET BRONX | Alteration | Filed — no permit on record | 01/10/2024 | — | Design EK ENGINEERING,P.C. Owner SHLEPPERS HOLDINGS LLC | — |
| X00961633 ↗ | 315 CASANOVA STREET BRONX | Alteration | Signed-off | 12/22/2023 | 01/04/2024 | Design EK ENGINEERING,P.C. Contractor TAINO MECHANICAL CONTRACT | DESIGN FOR THE REPLACEMENT OF TWO ROOF TOP AC UNITS FOR THE BUILDING AS SHOWN ON PLANS. THERE IS NO CHANGE IN USE, OCCUPANCY OR MEANS OF EGR… |
| B00776705 ↗ | 1279 ST JOHNS PLACE BROOKLYN | Alteration | Permit Issued | 10/31/2022 | 10/13/2023 | Design EK ENGINEERING,P.C. Owner JEMCAP Contractor WAXTEL LLC Filer S&M EXPEDITING | INSTALLATION OF SPLIT DX AC SYSTEMS FOR THE BUILDING. DESIGN INCLUDES INDOOR & OUTDOOR UNITS, REFRIDGERANT PIPING, CONSENDATE PIPING, PIPING… |
| Q00776769 ↗ | 36-32 MAIN STREET QUEENS | Alteration | Signed-off | 10/20/2022 | 12/02/2022 | Design EK ENGINEERING,P.C. Contractor CONTINENTAL NETWORK CORP | DESIGN FOR THE INSTALLATION OF ONE SPLIT DX AC SYSTM FOR THE BUILDING. DESIGN INCLUDES INDOOR UNITS, OUTDOOR UNITS, REFRIGERANT PIPING, SUPP… |
| B00776685 ↗ | 1279 ST JOHNS PLACE BROOKLYN | Alteration | Filed — no permit on record | 10/31/2022 | — | Design EK ENGINEERING,P.C. Owner JEMCAP Filer S&M EXPEDITING | — |
| Q07995133 ↗ | 49-06 SKILLMAN AVENUE QUEENS | Alteration | Signed-off | 09/16/2022 | 10/05/2022 | Design EK ENGINEERING,P.C. Contractor NICHOLAS A. CANTATORE Filer S&M EXPEDITING | DESIGN FOR 1 NEW OIL-FIRED HOT WATER BOILER AS SHOWN ON PLANS. INCLUDING FUEL OIL TANK, FUEL OIL PIPING AND HOT WATER PIPING. THERE IS NO CH… |
| Q00528532 ↗ | 121-07 SUTPHIN BOULEVARD QUEENS | Alteration | Signed-off | 06/14/2021 | 07/20/2021 | Design EK ENGINEERING,P.C. Contractor LOVE YOUR HOME CONTRACTIN Filer S&M EXPEDITING | INSTALL NEW HVAC UNIT. THERE IS NO CHANGE IN USE, OCCUPANCY OR MEANS OF EGRESS |
| B00527554 ↗ | 575 5 AVENUE BROOKLYN | Alteration | Signed-off | 06/12/2021 | 07/19/2021 | Design EK ENGINEERING,P.C. Contractor AIDEN HVAC MECHANICAL INC | Installation of new HVAC system for 1st fl. commercial space as shown on plans. No change in use, egress or occupancy |
| B00450253 ↗ | 7201 4 AVENUE BROOKLYN | Alteration | Signed-off | 03/31/2021 | 07/13/2021 | Design MARK VETTER ARCHITECTURE Contractor ARROW CONSTRUCTION CONSULTANTS Filer S&M EXPEDITING | INSTALLATION OF NEW VENT FOR DRYER & RELOCATION OF BATHROOM VENT. THERE IS NO CHANGE IN SUE, OCCUPANCY OR MEANS OF EGRESS. |
| Q00468616 ↗ | 242-11 VAN ZANDT AVENUE QUEENS | Alteration | Signed-off | 03/01/2021 | 05/28/2021 | Design EK ENGINEERING,P.C. Contractor RIGHT TEMP MECHANICAL INC | Design for the installation of two split DX AC systems for the building. Design includes indoor units, ducts, outdoor units, refrigerant pip… |
| Q00468637 ↗ | 242-11 VAN ZANDT AVENUE QUEENS | Alteration | Signed-off | 03/01/2021 | 05/25/2021 | Design EK ENGINEERING,P.C. Contractor MATHEW WEISS | Project includes partial domestic hot and cold water piping, gas piping, supports ,fittings, valves, etc. New indirect fired domestic hot wa… |
| M00193365 ↗ | 71 BROADWAY MANHATTAN | Alteration | Filed — no permit on record | 10/28/2019 | — | Design EK ENGINEERING,P.C. Owner EQUITY RESIDENTIAL Filer S&M EXPEDITING | — |
| Building | Filings | Most Recent |
|---|---|---|
| 151 COURT STREET ↗ | 2 | 08/14/2026 |
| 2459 FREDRICK DOUGLASS BL ↗ | 1 | 01/07/2026 |
| 441 EAST 164 STREET ↗ | 1 | 01/10/2024 |
| 434 EAST 165 STREET ↗ | 1 | 01/10/2024 |
| 315 CASANOVA STREET ↗ | 1 | 12/22/2023 |
| 49-06 SKILLMAN AVENUE ↗ | 2 | 12/01/2022 |
| 1279 ST JOHNS PLACE ↗ | 3 | 10/31/2022 |
| 36-32 MAIN STREET ↗ | 1 | 10/20/2022 |
| 7201 4 AVENUE ↗ | 2 | 02/24/2022 |
| 121-07 SUTPHIN BOULEVARD ↗ | 2 | 08/08/2021 |
| 242-11 VAN ZANDT AVENUE ↗ | 3 | 07/28/2021 |
| 575 5 AVENUE ↗ | 1 | 06/12/2021 |
| 71 BROADWAY ↗ | 1 | 10/28/2019 |
| Date | Requirement | Building | Inspector | Role |
|---|---|---|---|---|
| 06/02/2026 | HVAC-R and service water heating system controls | 151 COURT STREET | EDWARD KAJA | energy_progress |
| 06/02/2026 | HVAC-R and service water heating equipment | 151 COURT STREET | EDWARD KAJA | energy_progress |
| 04/07/2026 | Final | 151 COURT STREET | EDWARD KAJA | progress |
| 04/07/2026 | Mechanical Systems | 151 COURT STREET | EDWARD KAJA | special |
| 01/22/2026 | Final | 151 COURT STREET | EDWARD KAJA | progress |
| 01/22/2026 | Mechanical Systems | 151 COURT STREET | EDWARD KAJA | special |
| 01/06/2026 | Mechanical Systems | 2459 FREDRICK DOUGLASS BL | EDWARD KAJA | special |
| 01/06/2026 | Final | 2459 FREDRICK DOUGLASS BL | EDWARD KAJA | progress |
| 01/07/2024 | Fire-Resistant Penetrations and Joints | 434 EAST 165 STREET | EDWARD KAJA | special |
| 01/07/2024 | Energy Code Compliance Inspections | 434 EAST 165 STREET | EDWARD KAJA | progress |
| 10/07/2023 | Final | 434 EAST 165 STREET | EDWARD KAJA | progress |
| 10/07/2023 | Mechanical Systems | 434 EAST 165 STREET | EDWARD KAJA | special |
| 01/07/2023 | Fire-Resistant Penetrations and Joints | 1279 ST JOHNS PLACE | EDWARD KAJA | special |
| 12/06/2022 | HVAC-R and service water heating system controls | 49-06 SKILLMAN AVENUE | EDWARD KAJA | energy_progress |
| 12/06/2022 | HVAC-R and service water piping design and insulation | 49-06 SKILLMAN AVENUE | EDWARD KAJA | energy_progress |
| 12/06/2022 | HVAC-R and service water heating equipment | 49-06 SKILLMAN AVENUE | EDWARD KAJA | energy_progress |
| 12/06/2022 | Fire-Resistant Penetrations and Joints | 49-06 SKILLMAN AVENUE | EDWARD KAJA | special |
| 12/06/2022 | Fuel-Oil Storage and Fuel-Oil Piping Systems | 49-06 SKILLMAN AVENUE | EDWARD KAJA | special |
| 12/06/2022 | Heating Systems | 49-06 SKILLMAN AVENUE | EDWARD KAJA | special |
| 11/28/2022 | HVAC-R and service water heating system controls | 49-06 SKILLMAN AVENUE | EDWARD KAJA | energy_progress |
| 11/28/2022 | HVAC-R and service water heating equipment | 49-06 SKILLMAN AVENUE | EDWARD KAJA | energy_progress |
| 11/28/2022 | HVAC-R and service water piping design and insulation | 49-06 SKILLMAN AVENUE | EDWARD KAJA | energy_progress |
| 11/28/2022 | Heating Systems | 49-06 SKILLMAN AVENUE | EDWARD KAJA | special |
| 11/28/2022 | Fuel-Oil Storage and Fuel-Oil Piping Systems | 49-06 SKILLMAN AVENUE | EDWARD KAJA | special |
| 11/28/2022 | Fire-Resistant Penetrations and Joints | 49-06 SKILLMAN AVENUE | EDWARD KAJA | special |
| 07/18/2022 | Final | 36-32 MAIN STREET | EDWARD KAJA | progress |
| 07/18/2022 | Mechanical Systems | 36-32 MAIN STREET | EDWARD KAJA | special |
| 03/01/2022 | Mechanical Systems | 7201 4 AVENUE | EDWARD KAJA | special |
| 03/01/2022 | Final | 7201 4 AVENUE | Mark Vetter | progress |
| 02/14/2022 | Mechanical Systems | 7201 4 AVENUE | EDWARD KAJA | special |
| 02/14/2022 | Final | 7201 4 AVENUE | Mark Vetter | progress |
| 08/02/2021 | HVAC-R and service water heating equipment | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | energy_progress |
| 08/02/2021 | HVAC-R and service water piping design and insulation | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | energy_progress |
| 08/02/2021 | HVAC-R and service water heating system controls | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | energy_progress |
| 08/02/2021 | Fire-Resistant Penetrations and Joints | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | special |
| 07/27/2021 | HVAC-R and service water heating system controls | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | energy_progress |
| 07/27/2021 | HVAC-R and service water piping design and insulation | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | energy_progress |
| 07/27/2021 | HVAC-R and service water heating equipment | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | energy_progress |
| 07/27/2021 | Fire-Resistant Penetrations and Joints | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | special |
| 02/14/2021 | HVAC-R and service water heating equipment | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | energy_progress |
| 02/14/2021 | Duct leakage testing, insulation and design | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | energy_progress |
| 02/14/2021 | Energy Code Compliance Inspections | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | progress |
| 02/14/2021 | Energy Code Compliance | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | progress |
| 02/14/2021 | Heating Systems | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | special |
| 02/14/2021 | Fire-Resistant Penetrations and Joints | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | special |
| 02/14/2021 | HVAC-R and service water piping design and insulation | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | energy_progress |
| 02/14/2021 | HVAC-R and service water heating system controls | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | energy_progress |
| 02/10/2021 | Mechanical Systems | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | special |
| 02/10/2021 | Final | 242-11 VAN ZANDT AVENUE | EDWARD KAJA | progress |