| Owner | Filings | Most Recent |
|---|---|---|
| Vornado Realty Trust | 1,484 | 10/04/2026 |
| 888 Seventh Ave | 149 | 03/22/2026 |
| Paramount Group | 37 | 03/21/2026 |
| 888 7th Ave Associates | 31 | 03/21/2026 |
| 888 7th Ave Associates Paramount Group | 3 | 03/21/2026 |
| 1010 Wins New Radio | 1 | 03/21/2026 |
| AGT | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Always Fast Services | 1 | 10/02/2026 |
| Goldman Copeland Associates | 78 | 09/15/2026 |
| Ware Malcomb | 6 | 09/09/2026 |
| TPG Architecture | 4 | 08/18/2026 |
| CFS Engineering | 8 | 08/14/2026 |
| Gilsanz Murray Steficek | 6 | 07/01/2026 |
| Interior Management | 1 | 09/16/2025 |
| MG Engineering | 24 | 01/23/2024 |
| Sdga | 2 | 01/23/2024 |
| Randall P. Collins Architect | 17 | 05/01/2023 |
| Samir Awad Architect | 1 | 04/28/2023 |
| Severud Associates Consulting Engineering | 4 | 03/20/2023 |
| Gensler | 2 | 01/31/2023 |
| Nelson Architecture & Interiors | 3 | 12/16/2022 |
| Fogarty Finger Architecture | 3 | 12/13/2022 |
| Loffredo Brooks Architects | 1 | 09/20/2022 |
| Robert Derector Associates | 3 | 08/16/2022 |
| Etna Consulting | 1 | 06/11/2021 |
| F.p.villano Consulting Engineering | 2 | 01/25/2021 |
| 2LS Consulting Engineering | 3 | 01/09/2020 |
| Tohfaz Uddin PE | 2 | 07/22/2019 |
| Jose L. Pena, P.E | 2 | 04/18/2019 |
| Representative | Filings | Most Recent |
|---|---|---|
| Rizzo Group | 9 | 03/21/2026 |
| Archetype Consultants | 284 | 03/21/2026 |
| Louis Striar | 8 | 03/21/2026 |
| Milrose Consultants | 8 | 03/21/2026 |
| A1 Expediting Service | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Clune Construction Co | General Contractor | 64 | 07/10/2026 |
| Ambassador Construction | General Contractor | 17 | 07/08/2026 |
| L&K Partners | General Contractor | 15 | 07/08/2026 |
| Skyline Fire Sprinkler Co | Fire Protection | 11 | 07/08/2026 |
| S.B.A. Plumbing | Plumbing | 11 | 07/08/2026 |
| Americon Construction | General Contractor | 10 | 04/09/2026 |
| Par Plumbing Co., Inc.o | Fire Protection | 7 | 03/21/2026 |
| York Scaffold Equipment | Scaffold | 6 | 07/08/2026 |
| Abco-Peerless Sprinkler | Fire Protection | 5 | 07/08/2026 |
| Par Plumbing Co | Plumbing | 5 | 07/08/2026 |
| Structure Tone | General Contractor | 4 | 07/08/2026 |
| Full Capacity Fire | Fire Protection | 4 | 07/08/2026 |
| Polo Electric Corp D/B/A | Electrical | 4 | 03/21/2026 |
| Lab Plumbing & Heating Co | Plumbing | 4 | 07/08/2026 |
| Icon Interiors | General Contractor | 4 | 03/21/2026 |
| PSI Partners | Fire Protection | 4 | 07/08/2026 |
| Polo Electric Corp D/B/A | Electrical | 3 | 03/22/2026 |
| A&A Plumbing | Plumbing | 3 | 08/11/2026 |
| Omara Organization | General Contractor | 3 | 07/08/2026 |
| James E Fitzgerald | General Contractor | 3 | 07/08/2026 |
| BP Mechanical | specialty_contractor | 3 | 07/08/2026 |
| Addison Plumbing and Heating | Plumbing | 3 | 07/08/2026 |
| Village Electl Contractors | Electrical | 2 | 03/21/2026 |
| Allstate Electrical Cont | Electrical | 2 | 03/22/2026 |
| John Gallin & Son | General Contractor | 2 | 07/08/2026 |
| JT Magen & Company | General Contractor | 2 | 07/08/2026 |
| W5 Group | General Contractor | 2 | 03/21/2026 |
| L.S. Sign Co | Sign hanger | 2 | 07/08/2026 |
| Red Hook Sign and Electric | Sign hanger | 2 | 07/08/2026 |
| Bedrock Mechanical | Fire Protection | 2 | 09/18/2026 |
| Manengeering Bureau | Fire Protection | 2 | 07/08/2026 |
| Mill Brook Fire Protection | Fire Protection | 2 | 07/08/2026 |
| Par Fire Protection | Fire Protection | 2 | 07/08/2026 |
| Parkview P&H | Plumbing | 2 | 07/08/2026 |
| Adco Electrical | Electrical | 1 | 03/21/2026 |
| Aggressive Fire Protection | Fire Protection | 1 | 07/08/2026 |
| Sirina Fire Protection | Fire Protection | 1 | 07/08/2026 |
| Donato Plumbing | Plumbing | 1 | 07/08/2026 |
| Lliguichushca Jose | Electrical | 1 | 03/21/2026 |
| KG Sprinkler | Fire Protection | 1 | 07/08/2026 |
| Nead Electric | Electrical | 1 | 03/21/2026 |
| Lipsky & Rosenthal | Plumbing | 1 | 07/08/2026 |
| RNH Electric Company | Electrical | 1 | 03/21/2026 |
| Standard Fire Protection | Fire Protection | 1 | 07/08/2026 |
| Tower Fire Protection | Fire Protection | 1 | 07/08/2026 |
| William C. Gerakaris P&H | Plumbing | 1 | 07/08/2026 |
| Vision 21 | General Contractor | 1 | 09/23/2026 |
| J.H. Electric of New York | Electrical | 1 | 03/21/2026 |
| Andamio Scaffolding | Scaffold | 1 | 10/03/2026 |
| Structural Preserv System | General Contractor | 1 | 06/02/2026 |
| C. W. Greene | Electrical | 1 | 03/22/2026 |
| Allstate Electrical Cont | Electrical | 1 | 03/21/2026 |
| Colgate Restoration | specialty_contractor | 1 | 08/26/2026 |
| CLS Project Solutions | General Contractor | 1 | 09/15/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Broadway Inspections | 8735 | 3 | 09/15/2026 |
| Socotec Engineering | 4983 | 6 | 08/18/2026 |
| Hansen Engineering | 8174 | 40 | 07/01/2026 |
| Milrose Consultants | 2003 | 1 | 09/16/2025 |
| Gilsanz Murray Steficek | 240 | 1 | 08/18/2025 |
| DNA Controlled Inspection | 554 | 3 | 04/28/2025 |
| MEP Inspections | 1102 | 6 | 05/15/2023 |
| Alan D Marcus, PE | 1761 | 24 | 05/01/2023 |
| Coastal Construction Service | 3827 | 15 | 01/20/2023 |
| Becker Engineering | 633 | 35 | 12/13/2022 |
| G&G Sprinkler Services | 2782 | 2 | 08/16/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Permit Issued | Andamio Scaffolding | 10/02/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Vision 21 | 09/22/2026 |
| DOB NOW | Sprinklers | Permit Issued | Bedrock Mechanical | 09/17/2026 |
| DOB NOW | General Construction | Permit Issued | CLS Project Solutions | 09/14/2026 |
| DOB NOW | Plumbing | Permit Issued | A&A Plumbing | 08/10/2026 |
| DOB NOW | General Construction | Permit Issued | Colgate Restoration | 08/04/2026 |
| DOB NOW | Sprinklers | Permit Issued | Bedrock Mechanical | 07/20/2026 |
| DOB NOW | Structural | Permit Issued | Clune Construction Co | 07/08/2026 |
| DOB NOW | General Construction | Permit Issued | Clune Construction Co | 07/06/2026 |
| DOB NOW | Structural | Permit Issued | Clune Construction Co | 07/06/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Clune Construction Co | 07/01/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Americon Construction | 12/23/2025 |
| DOB NOW | General Construction | Signed-off | Americon Construction | 12/19/2025 |
| DOB NOW | Sprinklers | Permit Issued | H M Sprinkler | 12/16/2025 |
| DOB NOW | Plumbing | Permit Issued | Donato Plumbing | 12/16/2025 |
| DOB NOW | General Construction | Signed-off | Clune Construction Co | 10/02/2025 |
| DOB NOW | Structural | Permit Issued | Structural Preserv System | 09/24/2025 |
| DOB NOW | Sprinklers | Permit Issued | Mora Fire Protection | 08/12/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | Clune Construction Co | 07/23/2025 |
| DOB NOW | General Construction | Permit Issued | Clune Construction Co | 07/22/2025 |
| DOB NOW | Suspended Scaffold | Permit Issued | Colgate Restoration | 03/10/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Omara Organization | 08/15/2024 |
| DOB NOW | Sprinklers | Signed-off | Mora Fire Protection | 08/12/2024 |
| DOB NOW | General Construction | Signed-off | Omara Organization | 08/01/2024 |
| DOB NOW | Plumbing | Signed-off | A&A Plumbing | 08/01/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | Colgate Restoration | 03/12/2024 |
| DOB NOW | Sprinklers | Signed-off | Leguci Piping & Heating | 10/23/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Clune Construction Co | 09/29/2023 |
| DOB NOW | General Construction | Signed-off | Clune Construction Co | 09/27/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Americon Construction | 08/11/2023 |
| DOB NOW | General Construction | Signed-off | Americon Construction | 08/11/2023 |
| DOB NOW | Plumbing | Signed-off | Parkview P&H | 06/10/2023 |
| DOB NOW | Sprinklers | Signed-off | Mora Fire Protection | 06/08/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Clune Construction Co | 06/01/2023 |
| DOB NOW | General Construction | Signed-off | Clune Construction Co | 05/30/2023 |
| DOB NOW | Sprinklers | Signed-off | Mora Fire Protection | 05/09/2023 |
| DOB NOW | General Construction | Signed-off | Clune Construction Co | 05/04/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Clune Construction Co | 05/04/2023 |
| DOB NOW | General Construction | Signed-off | W5 Group | 05/03/2023 |
| DOB NOW | Sprinklers | Signed-off | Standard Fire Supp | 05/01/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/15/2026 | Permit Issued | Vision 21 | Heating and Air Conditioning Systems | Heat / Cool Bosch MAKE: BOSCH, MODEL #CL012-HZ 10,900 BTU · Wshp ×1 |
| 07/22/2025 | Permit Issued | Clune Construction Co | Air Conditioning Systems | Cooling Bosch CL048-VT 4 tons · Wshp ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/15/2026 | Permit Issued | Bedrock Mechanical | — |
| 08/14/2026 | Permit Issued | KG Sprinkler | 67 heads |
| 07/22/2025 | Permit Issued | PSI Partners | 21 heads |
| 02/28/2020 | Signed-off | Skyline Fire Sprinkler Co | 149 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/15/2026 | — | — | — |
| 07/22/2025 | — | — | — |
| 07/14/2021 | Permit Issued | Par Plumbing Co | Gas |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/09/2026 | Complete | Polo Electric Corp D/B/A | General Wiring |
| 08/26/2026 | Permit Issued | Ronan Electrical | General Wiring |
| 08/06/2026 | Permit Issued | Borowide Elect'l Contractors | — |
| 04/02/2026 | Complete | Allstate Electrical Cont | General Wiring |
| 08/07/2025 | Complete | Cloonagh Electrical | General Wiring |
| 04/18/2025 | Permit Issued | Polo Electric Corp D/B/A | General Wiring |
| 08/07/2024 | Complete | MRD Electrical Services | General Wiring |
| 09/19/2023 | Complete | Allstate Electrical Cont | General Wiring |
| 08/28/2023 | Permit Issued | DNR Electric | General Wiring |
| 06/02/2023 | Complete | Allstate Electrical Cont | General Wiring |
| 05/24/2023 | Complete | Polo Electric Corp D/B/A | General Wiring |
| 05/08/2023 | Complete | Polo Electric Corp D/B/A | General Wiring |
| 01/03/2023 | Complete | Live Wire Electric 1 | General Wiring |
| 12/12/2022 | Complete | Polo Electric Corp D/B/A | General Wiring |
| 11/08/2022 | Complete | Nead Electric | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/01/2026 | Permit Issued | Clune Construction Co | Steel, Concrete |
| 09/22/2025 | Permit Issued | Clune Construction Co | Steel |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/02/2026 | Permit Issued | Andamio Scaffolding | Sidewalk Shed |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/15/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/13/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/10/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/05/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/05/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/05/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 11/18/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/18/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/08/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/26/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 06/10/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 06/05/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 03/08/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 03/04/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/07/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/22/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 12/07/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/07/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 12/04/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 12/04/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 11/28/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 11/28/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/27/2023 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/24/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/12/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/19/2026 | Fire-Resistant Penetrations and Joints | ALEXIS SCHLESSINGERMAN | special |
| 08/19/2026 | Final | ALEXIS SCHLESSINGERMAN | progress |
| 08/17/2026 | Fire-Resistant Penetrations and Joints | ALEXIS SCHLESSINGERMAN | special |
| 08/17/2026 | Post-installed Anchors | ALEXIS SCHLESSINGERMAN | special |
| 08/17/2026 | Sprinkler Systems | ALEXIS SCHLESSINGERMAN | special |
| 08/06/2026 | Sprinkler Systems | Salvatore Chiarelli | special |
| 08/04/2026 | Energy Code Compliance Inspections | Salvatore Chiarelli | progress |
| 08/04/2026 | Final | Salvatore Chiarelli | progress |
| 08/04/2026 | Mechanical Systems | Salvatore Chiarelli | special |
| 08/04/2026 | Fire-Resistant Penetrations and Joints | Salvatore Chiarelli | special |
| 08/04/2026 | Final | Salvatore Chiarelli | progress |
| 08/04/2026 | HVAC-R and service water piping design and insulation | Salvatore Chiarelli | energy_progress |
| 08/04/2026 | HVAC-R and service water heating equipment | Salvatore Chiarelli | energy_progress |
| 08/04/2026 | Fire-Resistant Penetrations and Joints | Salvatore Chiarelli | special |
| 07/02/2026 | Final | ALEXIS SCHLESSINGERMAN | progress |
| 07/02/2026 | Fire-Resistant Penetrations and Joints | ALEXIS SCHLESSINGERMAN | special |
| 07/01/2026 | Structural Steel - Welding | Ryan Hansen | special |
| 07/01/2026 | Structural Steel - Details | Ryan Hansen | special |
| 07/01/2026 | Final | Ryan Hansen | progress |
| 07/01/2026 | Structural Steel - High Strength Bolting | Ryan Hansen | special |
| 07/01/2026 | Concrete - Cast-In-Place | Ryan Hansen | special |
| 07/01/2026 | Structural Stability – Alterations of existing buildings | Ryan Hansen | special |
| 07/01/2026 | Sprayed fire-resistant materials | Ryan Hansen | special |
| 05/01/2026 | Final | Susanne Mackiw | progress |
| 04/30/2026 | Final | Susanne Mackiw | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| JS Capital/One Madison | Office | Floors 39, 40 | Project M01386842 Project M01386859 Project M01386869 Project M01386880 Project M01391297 |
| Hudson Advisors | Office | Floors 17, 18 | Project M01315652 Project M01315740 Project M01315758 Project M01315764 Project M00830487 Project M00830520 Project M00830544 Project M00830562 |
| Grace & Mercy | Office | Sub-cellar, Floor 21 | Project M01271661 Project M01241045 Project M01241050 Project M01241025 |
| Womble Bond Dickinson | Office | Floor 38 | Project M01255505 |
| Cynosure | Office | Floor 23 | Project M01066073 Project M01066080 Project M01066083 Project M01066085 |
| Top | Office | Floors 28, 41, 42 | Project M00926026 Project M00926031 Project M00926021 Project M00776487 Project M00776496 Project M00776508 Project M00777305 Project M00777317 Project M00777325 Project M00777336 Project M00518441 Project M00518502 |
| Castle Lake | Office | Floor 24 | Project M00872508 Project M00872513 |
| CastleKnight | Office | Floor 24 | Project M00872503 Project M00872498 |
| Vornado | Office | Floors 16–18 | Project M08037486 Project M08037499 Project M08037445 Project M08037459 Project M00587036 Project M00586990 Project M00587020 Project M00587042 |
| H.Partners | Office | Floor 29 | Project M00789468 Project M00788567 Project M00788630 Project M00788639 |
| United Talent Agency | Office | Floors 8, 9 | Project M00775715 Project M00775725 Project M00775728 Project M00775612 Project M00275645 Project M00275655 Project M00275714 |
| Boulder Hill | Office | Floor 27 | Project M00755496 Project M00755485 Project M00755489 Project M00755503 |
| Protiviti | Office | Floors 12, 13 | Project M00733491 Project M00733495 Project M00733500 Project M00733504 |
| TZP Management Group | Office | Floor 20 | Project M00636666 Project M00636678 Project M00636696 Project M00636724 |
| Joho Capital | Office | Floor 28 | Project M00600173 Project M00600180 Project M00600184 Project M00600187 |
| QVT Financial | Office | Floor 43 | Project M00576420 Project M00576427 Project M00576429 Project M00576434 |
| Hain Park Capital | Office | Floor 41 | Project M00540542 Project M00540557 Project M00540566 Project M00540577 |
| Archegos | Office | Floors 22, 38 | Project M00338677 Project M00338688 Project M00292338 Project M00292356 Project M00292531 |
| A88M Fitness | Fitness / Recreation | Floor 42 | Project M00310409 Project M00310507 |
| Peak 6 Investments | Office | Floor 32 | Project M00223109 Project M00222665 Project M00222734 |
| Redeye Grill | Restaurant / Food Service | Floors 1–5 | Project M00147820 Project M00147831 |