| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| S01462421 | 800 CASTLETON AVENUE STATEN ISLAND | Alteration | Filed — no permit on record | 09/29/2026 | — | Design BOHLER ENGINEERING NY PLLC Filer BOHLER ENGINEERING | — |
| S01466750 | 800 CASTLETON AVENUE STATEN ISLAND | Alteration | Filed — no permit on record | 09/29/2026 | — | Design BOHLER ENGINEERING NY PLLC Filer BOHLER ENGINEERING | — |
| S01050714 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 06/03/2024 | 09/24/2026 | Design PERMANENT ENGINEERING P.C. Contractor NKN CONSTRUCTION INC Filer PERMANENT ENGINEERING | Facade restoration at existing six story Main building. Replacement of existing parapet wall at perimeter of existing roof indicated at Main… |
| S00724254 | 355 BARD AVENUE STATEN ISLAND | Alteration | Permit Issued | 08/18/2026 | 09/21/2026 | Design ALEXANDER BADALAMENTI Contractor NKN CONSTRUCTION INC | SLB Bldg-ARCHITECTURAL WORK FOR PROPOSED ROOF REPLACEMENT FOR SLB BUILDING -- 3RD FLOOR AND 5TH FLOOR ROOF SETBACKS-- LOCATED AT RICHMOND UN… |
| S01112859 | 355 BARD AVENUE STATEN ISLAND | Alteration | Permit Issued | 10/22/2024 | 09/04/2026 | Design ALEXANDER BADALAMENTI Contractor NKN CONSTRUCTION INC | RUMC- STRUCTURAL WORK ASSOCIATED WITH ROOF COOLING TOWER REPLACEMENT, AS PER PLANS FILED HEREWITH; NO CHANGES TO EGRESS, USE OR OCCUPANCY. |
| S00881156 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 07/05/2023 | 08/25/2026 | Contractor AMERICON CONSTRUCTION INC. | RUMC-BI-PLANE EP LAB-SETON & SPELLMAN WINGS - Medical Use Bldg- Proposing Interior Reno on Floor #1 for new Cardiac Cath Labs, Impatient/Out… |
| Name | Projects together | Most recent |
|---|---|---|
| Lizardos Engineering | 10 | 11/06/2026 |
| Permanent Engineering | 10 | 07/25/2026 |
| Alexander Badalamenti | 7 | 11/06/2026 |
| Cannondesign | 6 | 01/19/2023 |
| Bohler Engineering NY | 5 | 11/06/2026 |
| A Tech Engineering NYC | 4 | 09/03/2025 |
| George Sigalos P.E. | 4 | 02/19/2025 |
| Leon Skvirsky PE | 4 | 09/11/2024 |
| Mark D. Lipton Associates | 2 | 07/29/2024 |
| TDM Consulting Engineering | 2 | 08/01/2025 |
| Active Design Group Engineering | 1 | 08/13/2026 |
| AK Consulting Services | 1 | 08/12/2025 |
| Daniel Schunkewitz Architect | 1 | 10/09/2026 |
| Gilsanz Murray Steficek | 1 | 10/09/2026 |
| GNP Design Group | 1 | 05/21/2025 |
| Levin Engineering | 1 | 07/19/2021 |
| Lilker Associates Consulting Engineering | 1 | 10/09/2026 |
| PCS Engineering | 1 | 11/27/2023 |
| R.G. Vanderweil Engineers | 1 | 08/13/2026 |
| Withdrawn | 1 | 10/25/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| NKN Construction | 13 | 08/18/2026 |
| Champion International | 4 | 02/19/2025 |
| MVS Heating & Air Condit | 4 | 09/03/2025 |
| L.F. Driscoll Company | 3 | 10/25/2022 |
| R.G.M. Signs | 3 | 04/01/2021 |
| Scaran Plumbing | 3 | 08/01/2025 |
| H&G Contracting | 2 | 12/08/2025 |
| Jpi Plumbing & Heating | 2 | 12/08/2025 |
| Manengeering Bureau | 2 | 01/19/2023 |
| MPC Plumbing & Heating | 2 | 05/17/2021 |
| Active Signs | 1 | 09/11/2024 |
| Aggressive Fire Protection | 1 | 10/09/2026 |
| Americon Construction | 1 | 10/09/2026 |
| Bedrock Plumbing & Heating | 1 | 09/19/2023 |
| Capital Contracting P&H | 1 | 10/09/2026 |
| Central Consulting | 1 | 10/09/2026 |
| Fresh Meadow Mechanical | 1 | 08/13/2026 |
| Latty's Gen Plumbing | 1 | 09/19/2023 |
| Manengeering Bureau | 1 | 01/19/2023 |
| Mercury Fire Supp | 1 | 11/05/2020 |
| New York Cooling Towers I | 1 | 05/21/2025 |
| PAR Plumbing | 1 | 02/26/2021 |
| Richmond Plumbing & Heating | 1 | 01/07/2025 |
| Sirina Fire Protection | 1 | 07/19/2021 |
| SKY Heights Construction | 1 | 08/12/2025 |
| Name | Projects together | Most recent |
|---|---|---|
| Permanent Engineering | 7 | 07/25/2026 |
| Bohler Engineering | 5 | 09/29/2026 |
| Conversano Associates | 5 | 10/25/2022 |
| Tarek M. Zeid, P.E. | 5 | 10/09/2026 |
| A Tech Engineering NYC | 3 | 09/03/2025 |
| Building Brothers | 3 | 04/01/2021 |
| JMV Associates | 2 | 12/08/2025 |
| Total Expediting | 2 | 02/19/2025 |
| AK Consulting Services | 1 | 08/12/2025 |
| Alexandra Consulting | 1 | 05/05/2021 |
| JMV Architect | 1 | 11/06/2026 |
| Louis Striar | 1 | 09/11/2024 |
| Orion Expediting | 1 | 07/19/2021 |
| Rpo | 1 | 05/21/2025 |
| Rigging Consultants | 1 | 11/27/2023 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| S01462421 | 800 CASTLETON AVENUE STATEN ISLAND | Alteration | Filed — no permit on record | 09/29/2026 | — | Design BOHLER ENGINEERING NY PLLC Filer BOHLER ENGINEERING | — |
| S01466750 | 800 CASTLETON AVENUE STATEN ISLAND | Alteration | Filed — no permit on record | 09/29/2026 | — | Design BOHLER ENGINEERING NY PLLC Filer BOHLER ENGINEERING | — |
| S01050714 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 06/03/2024 | 09/24/2026 | Design PERMANENT ENGINEERING P.C. Contractor NKN CONSTRUCTION INC Filer PERMANENT ENGINEERING | Facade restoration at existing six story Main building. Replacement of existing parapet wall at perimeter of existing roof indicated at Main… |
| S00724254 | 355 BARD AVENUE STATEN ISLAND | Alteration | Permit Issued | 08/18/2026 | 09/21/2026 | Design ALEXANDER BADALAMENTI Contractor NKN CONSTRUCTION INC | SLB Bldg-ARCHITECTURAL WORK FOR PROPOSED ROOF REPLACEMENT FOR SLB BUILDING -- 3RD FLOOR AND 5TH FLOOR ROOF SETBACKS-- LOCATED AT RICHMOND UN… |
| S01112859 | 355 BARD AVENUE STATEN ISLAND | Alteration | Permit Issued | 10/22/2024 | 09/04/2026 | Design ALEXANDER BADALAMENTI Contractor NKN CONSTRUCTION INC | RUMC- STRUCTURAL WORK ASSOCIATED WITH ROOF COOLING TOWER REPLACEMENT, AS PER PLANS FILED HEREWITH; NO CHANGES TO EGRESS, USE OR OCCUPANCY. |
| S00881156 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 07/05/2023 | 08/25/2026 | Contractor AMERICON CONSTRUCTION INC. | RUMC-BI-PLANE EP LAB-SETON & SPELLMAN WINGS - Medical Use Bldg- Proposing Interior Reno on Floor #1 for new Cardiac Cath Labs, Impatient/Out… |
| S01432525 | 355 BARD AVENUE STATEN ISLAND | Alteration | Filed — no permit on record | 07/25/2026 | — | Design PERMANENT ENGINEERING P.C. Filer PERMANENT ENGINEERING | — |
| S01226062 | 288 KISSEL AVENUE STATEN ISLAND | Alteration | Permit Issued | 07/30/2025 | 06/22/2026 | Design TDM CONSULTING ENGINEER Contractor NKN CONSTRUCTION INC | STRUCTURAL FILED TO INDICATE EMERG. ROOF REPLACEMENT OF RESIDENCE BLDG, REMOVING DOWN TO PARTIAL EXISTING BALLASTED ROOFING SYSTEM.INSTALL N… |
| S01345228 | 355 BARD AVENUE STATEN ISLAND | Alteration CO | Filed — no permit on record | 03/25/2026 | — | Design ALEXANDER BADALAMENTI Filer JMV ARCHITECT, PLLC | — |
| S01273866 | 800 CASTLETON AVENUE STATEN ISLAND | Alteration | Signed-off | 09/03/2025 | 10/02/2025 | Contractor MVS HEATING & AIR CONDIT | DIRECT REPLACEMENT OF (1) 7.5-TON HVAC SINGLE PACKAGE UNIT ONTO EXISTING ROOF CURB. |
| S01266367 | 669 CASTLETON AVENUE STATEN ISLAND | Alteration | Permit Issued | 08/12/2025 | 08/13/2025 | Design AK CONSULTING SERVICES, INC Contractor SKY HEIGHTS CONSTRUCTION | INSTALLATION OF TEMPORARY CONSTRUCTION FENCE AT 669 CASTLETON AVENUE STATEN ISLAND, NY 10301 AS INDICATED ON PLANS. THERE WILL BE NO CHANGE … |
| S01259498 | 355 BARD AVENUE STATEN ISLAND | Alteration | Permit Issued | 07/23/2025 | 07/31/2025 | Contractor FRESH MEADOW MECHANICAL C Filer BOHLER ENGINEERING | Structural work in conjunction with the Installation / retrofit of two selective catalytic reduction systems associated with the existing co… |
| S00947787 | 669 CASTLETON AVENUE STATEN ISLAND | Alteration | Signed-off | 11/15/2023 | 06/17/2025 | Design ALEXANDER BADALAMENTI Contractor H&G CONTRACTING CORP Filer JMV ASSOCIATES LLC | Proposed second floor renovations and upgrades. No change in use, egress, or occupancy. All as per plan filed herewith. |
| S00550588 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 07/20/2021 | 05/02/2025 | Design CANNONDESIGN Contractor MANENGEERING BUREAU INC Filer BOHLER ENGINEERING | INSTALLATON OF STANDPIPE |
| S01189925 | 355 BARD AVENUE STATEN ISLAND | Alteration | Filed — no permit on record | 03/12/2025 | — | Design BOHLER ENGINEERING NY PLLC Filer BOHLER ENGINEERING | — |
| S01173427 | 1161 VICTORY BOULEVARD STATEN ISLAND | Alteration | Signed-off | 02/19/2025 | 02/21/2025 | Design GEORGE SIGALOS P.E. Contractor CHAMPION INTERNATIONAL CO Filer TOTAL EXPEDITING LLC | INSTALLATION OF TWO MINI-SPLIT HEAT PUMPS. 24K AND 18K BTU |
| S01176182 | 800 CASTLETON AVENUE STATEN ISLAND | Alteration | Signed-off | 02/13/2025 | 02/18/2025 | Contractor MVS HEATING & AIR CONDIT | DIRECT REPLACEMENT OF (1) 7.5-TON HVAC SINGLE PACKAGE UNIT ONTO EXISTING ROOF CURB. |
| S01163761 | 355 BARD AVENUE STATEN ISLAND | Alteration | Permit Issued | 01/07/2025 | 01/08/2025 | Design GEORGE SIGALOS P.E. Contractor RICHMOND PLBG & HTG CO IN | INSTALLATION OF COMMERCIAL COOKING EQUIPMENT IN 1st FLOOR KITCHEN, REPLACEMENT OF GAS PIPING TO EXISTING COMMERCIAL COOKING EQUIPMENT. |
| S01054203 | 288 KISSEL AVENUE STATEN ISLAND | Alteration | Signed-off | 06/03/2024 | 12/09/2024 | Design PERMANENT ENGINEERING P.C. Contractor NKN CONSTRUCTION INC | Facade restoration at existing six story Residence building. Installation of masonry ties as perimeter of facade as indicated on plan.No c… |
| S01052171 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 06/03/2024 | 10/09/2024 | Design PERMANENT ENGINEERING P.C. Contractor NKN CONSTRUCTION INC Filer PERMANENT ENGINEERING | Facade restoration at existing SETON building. Installation of masonry ties and repointing of facade as indicated. Aluminum coping replace… |
| S01103191 | 800 CASTLETON AVENUE STATEN ISLAND | Alteration | Signed-off | 09/11/2024 | 09/18/2024 | Design LEON SKVIRSKY PE Contractor ACTIVE SIGNS INC Filer LOUIS STRIAR INC. | ILLUMINATED NON-ADVERTISING ACCESSORY WALL SIGN - IN PROPERTY LINES - RICHMOND UNIVERSITY MEDICAL CENTER. NO CHANGE OF USE, EGRESS OR OCCUPA… |
| S01091764 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 08/20/2024 | 08/22/2024 | Design GNP DESIGN GROUP Contractor NEW YORK COOLING TOWERS I Filer RPO INC. | COOLING TOWER REPLACEMENT AS PER PLANS FILED HEREWITH. NO CHANGES TO EGRESS, USE OR OCCUPANCY. |
| S00763429 | 355 BARD AVENUE STATEN ISLAND | Alteration | Permit Issued | 08/03/2022 | 04/09/2024 | Design ALEXANDER BADALAMENTI Contractor NKN CONSTRUCTION INC | SLB Bldg-EMERGENCY -Plumbing-WORK FOR 7th Floor Roof FOR SLB BUILDING LOCATED AT RICHMOND UNIVERSITY MEDICAL CENTER. ALL AS PER PLANS FILED… |
| S00942004 ↗ | 2935 VETERANS ROAD WEST STATEN ISLAND | Alteration | Signed-off | 10/03/2023 | 02/08/2024 | Design GEORGE SIGALOS P.E. Contractor JPI PLUMBING & HEATING IN | MODIFICATION TO EXISTING SPRINKLER SYSTEM AND PLUMBING IN CONJUNCTION WITH NEW INTERIOR LAYOUT FILED UNDER S00910818 |
| S00921237 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 09/14/2023 | 01/24/2024 | Design LIZARDOS ENGINEERING Contractor STRUCTURAL PRESERV SYSTEM Filer JMV ASSOCIATES LLC | Removal of existing medical gas piping and outlets within existing nurseries and to provide new medical gas piping and outlets to serve prop… |
| S00910818 ↗ | 2935 VETERANS ROAD WEST STATEN ISLAND | Alteration | Signed-off | 08/08/2023 | 01/23/2024 | Design MARK D. LIPTON ASSOCIATES Contractor H&G CONTRACTING CORP Filer TOTAL EXPEDITING LLC | Tenant Buildout of 1st Floor. Interior partitions only. |
| S00965798 | 355 BARD AVENUE STATEN ISLAND | Alteration | Filed — no permit on record | 11/27/2023 | — | Design PCS ENGINEERING | — |
| S00945327 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 10/26/2023 | 10/31/2023 | Contractor MVS HEATING & AIR CONDIT | DIRECT REPLACEMENT OF A 25-TON HVAC SPLIT-SYSTEM COMPRESSOR/CONDENSER UNIT ON GRADE |
| S00732127 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 07/27/2022 | 08/17/2023 | Design PERMANENT ENGINEERING P.C. Contractor NKN CONSTRUCTION INC Filer PERMANENT ENGINEERING | SLB BUILDING- SOUTH SIDE ELEVATION. Installation of brick work for existing facade, install weepholes every two feet of horizontal length an… |
| S00732336 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 11/28/2022 | 04/18/2023 | Design PERMANENT ENGINEERING P.C. Contractor NKN CONSTRUCTION INC | Subsequent filing filed for Structural work in conjunction with GC work type. Steel and support system for existing MH room. |
| S00745756 | 355 BARD AVENUE STATEN ISLAND | Alteration | Permit Issued | 11/01/2022 | 11/16/2022 | Design PERMANENT ENGINEERING P.C. Contractor NKN CONSTRUCTION INC Filer PERMANENT ENGINEERING | APPLICATION FILED TO ADDRESS VIOLATIONS AND REPAIR AND MAINTAIN BUILDING FIX CRACK/SPALLED/DETERIORATED AND SHIFTING/DISPLACING MASONRY. REP… |
| S00712021 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 04/28/2022 | 10/31/2022 | Design PERMANENT ENGINEERING P.C. Contractor NKN CONSTRUCTION INC Filer PERMANENT ENGINEERING | Application filed to resolve violation, work areas near the front entrance, that require repair. Underside of the overhang at the front ent… |
| S00462481 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 03/15/2021 | 08/23/2022 | Design CANNONDESIGN Contractor L.F. DRISCOLL COMPANY LLC | installation of mechanical systems |
| S00463798 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 03/15/2021 | 05/10/2022 | Design CANNONDESIGN Contractor MANENGEERING BUREAU INC | installation of 158 NEW SPRINKLER HEADS & 25 REMOVED SPRINKLER HEADS, 0 RELOCATED SPRINKLER HEADS |
| S00709478 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 04/14/2022 | 04/27/2022 | Design CANNONDESIGN Contractor L.F. DRISCOLL COMPANY LLC | MS - HVAC PERMIT APPLICATION FOR INSTALLATION OF TEMPORARY GENERATOR, FUEL OIL STORAGE DAYTANK AND ASSOCIATED PIPING. ARCH - REPAIR ALL PENE… |
| S00590797 | 355 BARD AVENUE STATEN ISLAND | Alteration | Permit Issued | 09/23/2021 | 03/14/2022 | Design PERMANENT ENGINEERING P.C. Contractor NKN CONSTRUCTION INC Filer PERMANENT ENGINEERING | Subsequent filing to include structural work at roof level of 6th floor. Replace spandrel beam and provide temporary shoring of edge of thre… |
| S00646548 | 1161 VICTORY BOULEVARD STATEN ISLAND | Alteration | Signed-off | 12/23/2021 | 03/09/2022 | Design GEORGE SIGALOS P.E. Contractor CHAMPION INTERNATIONAL CO | INSTALLATION OF MECHANICAL SYSTEMS IN CONJUNCTION WITH 520332934 DOC 04 |
| S00462494 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 02/26/2021 | 07/22/2021 | Design CANNONDESIGN Contractor PAR PLUMBING CO., INC | installation of plumbing fixtures and medical gas piping |
| S00536515 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 07/19/2021 | 07/20/2021 | Design LEVIN ENGINEERING PLLC Contractor SIRINA FIRE PROT CORP Filer ORION EXPEDITING LLC | RELOCATION OF EXISTING CONCEALED TO UPRIGHTS SPRINKLERS HEADS TO CREATE A TEMPORARY SPRINKLER EGRESS PROTECTION SYSTEM. AS PER PLANS SUBMITT… |
| S00378283 | 657 CASTLETON AVENUE STATEN ISLAND | Alteration | Signed-off | 02/12/2021 | 07/09/2021 | Design LIZARDOS ENGINEERING Contractor CHAMPION INTERNATIONAL CO Filer JMV ASSOCIATES LLC | PROPOSED MINOR INTERIOR RENOVATIONS TO EXISTING OFFICE SPACE. ALL AS PER PLAN FILED HERE WITH. |
| S00378301 | 657 CASTLETON AVENUE STATEN ISLAND | Alteration | Signed-off | 02/12/2021 | 06/29/2021 | Design LIZARDOS ENGINEERING Contractor MPC PLUMBING & HEATING IN Filer JMV ASSOCIATES LLC | PROPOSED GROUND FLOOR RENOVATIONS AND UPGRADES. ALL AS PER PLANS FILED HEREWITH. NO CHANGES IN USE, EGRESS OR OCCUPANCY. |
| S00514105 ↗ | 4434 AMBOY ROAD STATEN ISLAND | Alteration | Signed-off | 05/05/2021 | 05/10/2021 | Design MARK D. LIPTON ASSOCIATES Contractor Z N J CONSTRUCTION INC Filer ALEXANDRA CONSULTING | 2 new interior partitions |
| S00462446 | 355 BARD AVENUE STATEN ISLAND | Alteration | Permit Issued | 02/16/2021 | 03/23/2021 | Design PERMANENT ENGINEERING P.C. Contractor NKN CONSTRUCTION INC | Removal of 4 existing roof mounted exhaust and 1 glass and metal skylight on an existing concrete roof, to be selaed with concrete, located … |
| S00301070 ↗ | 1130 SOUTH AVENUE STATEN ISLAND | Alteration | Signed-off | 11/05/2020 | 03/03/2021 | Design LIZARDOS ENGINEERING Contractor CHAMPION INTERNATIONAL CO Filer JMV ASSOCIATES LLC | PROPOSE INTERIOR RENOVATION OF 2ND FLOOR. ALL AS PER PLANS FILED HEREWITH. OT( GENERAL CONSTRUCTION) AND PLUMBING FILED UNDER SEPARATE APP… |
| S00456772 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 01/21/2021 | 02/23/2021 | Design CANNONDESIGN Contractor L.F. DRISCOLL COMPANY LLC | APPLICATION FILED TO REMOVE, FLOORS, PARTITIONS, DOORS, FRAMES, CEILING, WALLS, MILL-WORK AND CRASH RAILS, PLUMBING AND MECHANICAL FIXTURES … |
| S00302220 ↗ | 1130 SOUTH AVENUE STATEN ISLAND | Alteration | Signed-off | 11/05/2020 | 12/17/2020 | Design LIZARDOS ENGINEERING Contractor MPC PLUMBING & HEATING IN Filer JMV ASSOCIATES LLC | PROPOSE INTERIOR RENOVATION OF 2ND FLOOR. ALL AS PER PLANS FILED HEREWITH. OT( GENERAL CONSTRUCTION) AND MECHANICAL FILED UNDER SEPARATE APP… |
| S00403094 | 355 BARD AVENUE STATEN ISLAND | Alteration | Signed-off | 10/20/2020 | 10/22/2020 | Contractor STREAMLINE CONSULTANTS NY | Installation of a new 10-ton Mitsubishi City Multi Outdoor Unit on grade. |
| S00076100 | 1161 VICTORY BOULEVARD STATEN ISLAND | Alteration | Signed-off | 09/17/2018 | 09/18/2018 | Design LEON SKVIRSKY PE Contractor R.G.M. SIGNS INC Filer BUILDING BROTHERS INC. | INSTALL NON-ILLUMINATED SIGN ON WALL (BREAST & WOMEN'S CENTER IMMEDIATE/PRIMARY CARE/WALK-IN) |
| S00076101 | 1161 VICTORY BOULEVARD STATEN ISLAND | Alteration | Signed-off | 09/17/2018 | 09/18/2018 | Design LEON SKVIRSKY PE Contractor R.G.M. SIGNS INC Filer BUILDING BROTHERS INC. | INSTALL ILLUMINATED SIGN ON WALL (THE KRISHNE URS MEDICAL PAVILIOM RICHMOND UNIVERSITY MEDICAL CENTER) |
| S00076102 | 1161 VICTORY BOULEVARD STATEN ISLAND | Alteration | Signed-off | 09/17/2018 | 09/18/2018 | Design LEON SKVIRSKY PE Contractor R.G.M. SIGNS INC Filer BUILDING BROTHERS INC. | INSTALL NON-ILLUMINATED SIGN ON WALL (BREAST & WOMEN'S CENTER IMMEDIATE/PRIMARY CARE/WALK-IN) |
| Building | Filings | Most Recent |
|---|---|---|
| 355 BARD AVENUE ↗ | 54 | 10/09/2026 |
| 800 CASTLETON AVENUE ↗ | 5 | 09/28/2026 |
| 669 CASTLETON AVENUE ↗ | 5 | 08/04/2025 |
| 288 KISSEL AVENUE ↗ | 4 | 05/14/2025 |
| 1161 VICTORY BOULEVARD ↗ | 7 | 01/29/2025 |
| 2935 VETERANS ROAD WEST ↗ | 5 | 09/27/2024 |
| 4434 AMBOY ROAD ↗ | 1 | 04/30/2021 |
| 657 CASTLETON AVENUE ↗ | 3 | 04/13/2021 |
| 1130 SOUTH AVENUE ↗ | 2 | 01/23/2020 |