| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q01372437 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Permit Issued | 04/08/2026 | 09/29/2026 | Design BURNS ENGINEERING, PC Owner NORTHWELL HEALTH Contractor CURRENT FIRE PROTECTION INC | Northwell LIJ Medical Center Sprinkler Project: sprinkler upgrades at portion of basement & 1st floor, as per plans filed herewith. |
| Q01402123 ↗ | 95-25 QUEENS BOULEVARD QUEENS | Alteration | Permit Issued | 06/25/2026 | 09/21/2026 | Design BLADYKAS ENGINEERING, P.C. Contractor ADI CONTRACTING LLC | NORTHWELL HEALTH: EXTENSION BH CLINIC: PROVIDE NEW AND MODIFY EXISTING HVAC SYSTEMS TO CONFORM WITH NEW SUITE LAYOUT, AS PER PLANS FILED HER… |
| Q01371982 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Permit Issued | 04/24/2026 | 08/25/2026 | Design BURNS ENGINEERING, PC Owner NORTHWELL HEALTH Contractor SIRINA FIRE PROT CORP | Northwell LIJ Sprinkler Upgrade project - Main Building: sprinkler upgrades throughout building, as per plans filed herewith. |
| M00872327 ↗ | 222 EAST 64 STREET MANHATTAN | Alteration | Permit Issued | 06/27/2023 | 08/07/2026 | Design LIZARDOS ENGINEERING Contractor CENTRAL CONSULTING & CONT | Northwell Health: Lab Relocation Project: modify Mechanical systems to conform with new layouts as per plans filed herewith. |
| M01230989 ↗ | 208 EAST 64 STREET MANHATTAN | Alteration | Permit Issued | 07/09/2025 | 08/06/2026 | Design ICOR ASSOCIATES Contractor SIRINA FIRE PROT CORP | Northwell Health Old MEETH: Sprinkler / Standpipe upgrades throughout building on floors indicated, including cap & removal of piping associ… |
| M08013299 ↗ | 1345 3 AVENUE MANHATTAN | New Building | Permit Issued | 10/03/2022 | 08/03/2026 | Design JAROS BAUM & BOLLES Contractor CONSIGLI CONSTRUCTION CO | Temporary Construction Fence with integrated noise mitigating barrier for New Building construction. |
| Person | Filings | Most recent |
|---|---|---|
| VINCENT FABIANO | 253 | 09/11/2026 |
| Name | Projects together | Most recent |
|---|---|---|
| LIZARDOS ENGINEERING | 37 | 07/28/2026 |
| GILSANZ MURRAY STEFICEK LLP | 19 | 04/17/2026 |
| PAMELA A. SMITH | 18 | 04/23/2026 |
| AKF ENGINEERS, LLP | 17 | 07/13/2026 |
| ICOR ASSOCIATES | 9 | 08/13/2026 |
| BURNS ENGINEERING, PC | 8 | 04/27/2026 |
| LORING CONSULTING ENGINEERS, INC. | 8 | 06/01/2026 |
| BLADYKAS ENGINEERING, P.C. | 7 | 06/25/2026 |
| JAROS BAUM & BOLLES | 7 | 09/03/2026 |
| THE LIRO GROUP | 5 | 04/30/2026 |
| GOLDMAN COPELAND ASSOCIATES | 4 | 09/23/2025 |
| LANGAN ENGINEERING | 4 | 09/03/2026 |
| MASCIONI & BEHRMANN, ARCHITECTURE & | 4 | 04/20/2026 |
| CANY ARCHITECTURE & ENGINEERING DPC | 3 | 12/02/2025 |
| KALLEN AND LEMELSON | 3 | 01/10/2024 |
| TPG ARCHITECTURE, LLP | 3 | 01/16/2025 |
| EWINGCOLE | 2 | 09/03/2026 |
| P.W. GROSSER CONSULTING | 2 | 09/04/2024 |
| SEVERUD ASSOCIATES | 2 | 09/03/2026 |
| STANTEC | 2 | 07/13/2022 |
| STEVEN PAUL HAMMER | 2 | 05/11/2020 |
| STUDIO A+T ARCHITECTS | 2 | 05/18/2023 |
| THE MCGUIRE GROUP ARCHITECTS | 2 | 12/19/2025 |
| ALEXANDER BADALAMENTI | 1 | 06/24/2026 |
| BOHLER ENGINEERING NY PLLC | 1 | 04/09/2026 |
| Name | Projects together | Most recent |
|---|---|---|
| SIRINA FIRE PROT CORP | 23 | 09/03/2026 |
| CENTRAL CONSULTING & CONT | 21 | 12/19/2025 |
| THE WHITING-TURNER CONTRA | 20 | 06/01/2026 |
| ALLIANCE PLUMBING CORP | 13 | 09/03/2026 |
| CAPITAL CONTR P&H CORP | 11 | 07/13/2026 |
| GILBANE BUILDING COMPANY | 11 | 11/19/2025 |
| HUNTER ROBERTS CONSTRUCTI | 11 | 04/23/2026 |
| CONSIGLI CONSTRUCTION CO | 8 | 09/03/2026 |
| PAR PLUMBING CO., INC | 8 | 09/02/2025 |
| ADI CONTRACTING LLC | 7 | 06/25/2026 |
| MACCARONE PLUMBING INC | 6 | 01/29/2026 |
| EMPIRE GENERAL CONTRACTIN | 5 | 09/26/2025 |
| L.F. DRISCOLL COMPANY LLC | 4 | 04/27/2026 |
| LENDLEASE(US)CONSTRUCTION | 4 | 09/03/2026 |
| NYC FIRE SPRINKLER CORP | 4 | 01/29/2026 |
| AMERICON CONSTRUCTION INC | 3 | 06/25/2026 |
| BOTTO MECHANICAL CORP | 3 | 06/26/2025 |
| CURRENT FIRE PROTECTION I | 3 | 04/08/2026 |
| ISLAND ACOUSTICS LLC | 3 | 01/16/2025 |
| JRB CONSTRUCTION CORP | 3 | 03/08/2023 |
| PAUL M MAINTENANCE INC | 3 | 05/18/2023 |
| VANGUARD CONSTRUCTION AND | 3 | 09/23/2025 |
| VILLAGE P & H NY INC | 3 | 01/12/2026 |
| ABCO PEERLESS SPRINKLER C | 2 | 09/02/2025 |
| AGGRESSIVE FIRE PROT LLC | 2 | 11/22/2022 |
| Name | Projects together | Most recent |
|---|---|---|
| NORTHWELL HEALTH | 97 | 06/01/2026 |
| NORTHWELL HEALTH LENOX HILL HOSPITA | 62 | 09/03/2026 |
| MATILDA AVE PROPERTY LLC | 4 | 05/18/2023 |
| BROADWALL MANAGEMENT | 3 | 04/20/2021 |
| FOREST HILLS PROPERTY GROUP LTD | 3 | 06/02/2026 |
| TENBER ASSOCIATES, L.P. | 3 | 04/06/2026 |
| CIMIAR REALTY LLC | 2 | 05/11/2020 |
| ROSENBAUM/ROSENFELD THIRD AVENUE PA | 2 | 05/06/2020 |
| STATEN ISLAND UNIVERSITY HOSPITAL | 2 | 10/15/2019 |
| 4 PARK AVE. ASSOCIATES LLC | 1 | 09/23/2025 |
| ALEXANDRIA REAL ESTATE EQUITIES | 1 | 09/01/2020 |
| LENOX COURT CONDOMINIUM | 1 | 02/12/2024 |
| LVP LIC HOTEL LLC | 1 | 03/11/2020 |
| MOLLOY COLLEGE | 1 | 07/25/2019 |
| SEA CREST NURSING AND REHABILITATIO | 1 | 04/23/2021 |
| Name | Projects together | Most recent |
|---|---|---|
| SUPPORT BUILDINGS OF NEW YORK | 2 | 06/05/2023 |
| Project | Address | Type | Status | Filed | Latest permit | On the project | Description |
|---|---|---|---|---|---|---|---|
| Q01372437 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Permit Issued | 04/08/2026 | 09/29/2026 | Design BURNS ENGINEERING, PC Owner NORTHWELL HEALTH Contractor CURRENT FIRE PROTECTION INC | Northwell LIJ Medical Center Sprinkler Project: sprinkler upgrades at portion of basement & 1st floor, as per plans filed herewith. |
| Q01402123 ↗ | 95-25 QUEENS BOULEVARD QUEENS | Alteration | Permit Issued | 06/25/2026 | 09/21/2026 | Design BLADYKAS ENGINEERING, P.C. Contractor ADI CONTRACTING LLC | NORTHWELL HEALTH: EXTENSION BH CLINIC: PROVIDE NEW AND MODIFY EXISTING HVAC SYSTEMS TO CONFORM WITH NEW SUITE LAYOUT, AS PER PLANS FILED HER… |
| Q01371982 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Permit Issued | 04/24/2026 | 08/25/2026 | Design BURNS ENGINEERING, PC Owner NORTHWELL HEALTH Contractor SIRINA FIRE PROT CORP | Northwell LIJ Sprinkler Upgrade project - Main Building: sprinkler upgrades throughout building, as per plans filed herewith. |
| M00872327 ↗ | 222 EAST 64 STREET MANHATTAN | Alteration | Permit Issued | 06/27/2023 | 08/07/2026 | Design LIZARDOS ENGINEERING Contractor CENTRAL CONSULTING & CONT | Northwell Health: Lab Relocation Project: modify Mechanical systems to conform with new layouts as per plans filed herewith. |
| M01230989 ↗ | 208 EAST 64 STREET MANHATTAN | Alteration | Permit Issued | 07/09/2025 | 08/06/2026 | Design ICOR ASSOCIATES Contractor SIRINA FIRE PROT CORP | Northwell Health Old MEETH: Sprinkler / Standpipe upgrades throughout building on floors indicated, including cap & removal of piping associ… |
| M08013299 ↗ | 1345 3 AVENUE MANHATTAN | New Building | Permit Issued | 10/03/2022 | 08/03/2026 | Design JAROS BAUM & BOLLES Contractor CONSIGLI CONSTRUCTION CO | Temporary Construction Fence with integrated noise mitigating barrier for New Building construction. |
| M01396745 ↗ | 222 EAST 64 STREET MANHATTAN | Alteration | Permit Issued | 06/23/2026 | 07/29/2026 | Design LIZARDOS ENGINEERING Contractor CONSIGLI CONSTRUCTION CO | Northwell New MEETH - O.R. Infrastructure Upgrades: Replacement of Air-Handling units AHU # 3, AHU # 4 and AHU # 5 as per plans filed herewi… |
| Q01371454 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Permit Issued | 04/21/2026 | 07/29/2026 | Design PAMELA A. SMITH Owner NORTHWELL HEALTH Contractor HUNTER ROBERTS CONSTRUCTION | Northwell LIJ Sprinkler Project - Research Wing: minor Architectural scope in conjunction with Sprinkler upgrades throughout building on flo… |
| Q01371463 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Permit Issued | 04/20/2026 | 07/28/2026 | Design PAMELA A. SMITH Owner NORTHWELL HEALTH Contractor HUNTER ROBERTS CONSTRUCTION | Northwell LIJ Sprinkler project - West Wing: minor Architectural scope in conjunction with Sprinkler upgrades throughout building on floors … |
| Q01371900 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Permit Issued | 04/08/2026 | 07/28/2026 | Design PAMELA A. SMITH Owner NORTHWELL HEALTH Contractor HUNTER ROBERTS CONSTRUCTION | Northwell LIJ Sprinkler project - Womens Hospital: minor Architectural scope in conjunction with Sprinkler upgrades throughout building on f… |
| Q01371434 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Permit Issued | 04/23/2026 | 07/27/2026 | Design PAMELA A. SMITH Owner NORTHWELL HEALTH Contractor HUNTER ROBERTS CONSTRUCTION | Northwell LIJ Medical Center Sprinkler Upgrade Project - Main Building: minor Architectural scope in conjunction with Sprinkler upgrades th… |
| Q01376478 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Permit Issued | 04/09/2026 | 07/21/2026 | Design BOHLER ENGINEERING NY PLLC Owner NORTHWELL HEALTH Contractor CONSIGLI CONSTRUCTION CO | Northwell LIJ Kaufman: civil site make-ready scope in OSP for existing courtyard renovations, as per plans filed herewith. |
| M01199162 ↗ | 20 7 AVENUE MANHATTAN | Alteration | Permit Issued | 12/02/2025 | 07/06/2026 | Contractor SKYLINE RESTORATION INC | Local Law 11/98 cycle 9B facade repairs with related parapet extension concrete work,. No change to use, egress or occupancy |
| Q00893878 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Permit Issued | 08/10/2023 | 06/24/2026 | Design LIZARDOS ENGINEERING Owner NORTHWELL HEALTH Contractor ABCO-PEERLESS SPRKLR CORP | Northwell LIJ Fire Pump Project: install final run of Fire Service piping @ Cellar Fire Pump Rm; install RPZ & misc. PL for same; install fi… |
| Q01080296 ↗ | 264-25 76 AVENUE QUEENS | New Building | Permit Issued | 10/17/2024 | 06/24/2026 | Design HANSEN ENGINEERING, PC Owner NORTHWELL HEALTH Contractor GILBANE BUILDING COMPANY | Northwell LIJ Medical Center: Water Service piping & Site Storm Drainage piping with associated installations for campus civil site work in … |
| Q01188855 ↗ | 102-01 66 ROAD QUEENS | Alteration | Permit Issued | 03/24/2025 | 06/24/2026 | Design BURNS ENGINEERING, PC Owner NORTHWELL HEALTH Contractor RAEL AUTOMATIC SPR.CO INC | Northwell Health Forest Hills Hospital: sprinkler upgrades throughout building, as per plans filed herewith. |
| Q01402092 ↗ | 95-25 QUEENS BOULEVARD QUEENS | Alteration | Filed — no permit on record | 06/24/2026 | — | Design ALEXANDER BADALAMENTI | — |
| Q01188791 ↗ | 102-01 66 ROAD QUEENS | Alteration | Permit Issued | 03/24/2025 | 06/23/2026 | Design PAMELA A. SMITH Owner NORTHWELL HEALTH Contractor GILBANE BUILDING COMPANY | Northwell Health Forest Hill Hospital: minor Architectural scope in conjunction with Sprinkler upgrades throughout building on floors indica… |
| Q01248672 ↗ | 270-05 76 AVENUE QUEENS | Alteration CO | Permit Issued | 09/29/2025 | 06/23/2026 | Design AKF ENGINEERS, LLP Owner NORTHWELL HEALTH Contractor GILBANE BUILDING COMPANY | Northwell LIJ Medical Center - Bone Marrow Transplant (BMT) Project: modify plumbing, sprinkler & standpipe systems to accommodate new hospi… |
| M01211842 ↗ | 208 EAST 64 STREET MANHATTAN | Alteration | Permit Issued | 06/04/2025 | 06/22/2026 | Design ICOR ASSOCIATES Contractor SIRINA FIRE PROT CORP | Northwell Health Old MEETH: Sprinkler / Standpipe upgrades throughout building on floors indicated, as per plans filed herewith. No change t… |
| M01082893 ↗ | 855 PARK AVENUE MANHATTAN | Alteration | Signed-off | 04/08/2025 | 06/17/2026 | Design JAROS BAUM & BOLLES Contractor ALLIANCE PLUMBING CORP | Northwell Lenox Hill: Wollman Lachman Pass Through Project: modify Plumbing and Sprinkler systems to conform with new interior layout as per… |
| Q01397913 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Permit Issued | 06/01/2026 | 06/11/2026 | Owner NORTHWELL HEALTH Contractor THE WHITING-TURNER CONTRA | Northwell LIJ EP Lab # 1: modify existing Mechanical systems to conform with hospital program renovations as per plans filed herewith. |
| M01282947 ↗ | 20 7 AVENUE MANHATTAN | Alteration | Signed-off | 09/18/2025 | 05/29/2026 | Design AKF ENGINEERS, LLP Contractor CAPITAL CONTR P&H CORP | Northwell Greenwich Village: STAT Lab project: modify Plumbing system at portion of existing cellar Lab space to conform with new hospital p… |
| M01116242 ↗ | 20 7 AVENUE MANHATTAN | Alteration | Permit Issued | 10/11/2024 | 05/28/2026 | Design GILSANZ MURRAY STEFICEK LLP Contractor CENTRAL CONSULTING & CONT | Northwell Health Greenwich Village: structural scope (framing of new wall opening for electrical conduit) in conjunction with new incoming C… |
| M01379851 ↗ | 855 PARK AVENUE MANHATTAN | Alteration | Signed-off | 04/17/2026 | 05/12/2026 | Design GILSANZ MURRAY STEFICEK LLP Contractor L.F. DRISCOLL COMPANY LLC | Northwell Lenox Hill: minor Structural scope in conjunction with Central Sterile HVAC upgrades. |
| M01379825 ↗ | 855 PARK AVENUE MANHATTAN | Alteration | Signed-off | 04/20/2026 | 05/11/2026 | Contractor L.F. DRISCOLL COMPANY LLC | Northwell Lenox Hill: minor architectural scope in conjunction with Central Sterile Supply HVAC upgrades, as per plans filed herewith. No ch… |
| M01103377 ↗ | 222 EAST 64 STREET MANHATTAN | Alteration | Permit Issued | 10/16/2024 | 05/04/2026 | Design LIZARDOS ENGINEERING Contractor SIRINA FIRE PROT CORP | Northwell New MEETH Emergency Generator & Quick Connect project: minor Sprinkler scope in conjunction with project, as per plans filed herew… |
| M01210868 ↗ | 222 EAST 64 STREET MANHATTAN | Alteration | Permit Issued | 06/10/2025 | 05/04/2026 | Design ICOR ASSOCIATES Contractor SIRINA FIRE PROT CORP | Northwell Health New MEETH: Sprinkler / Standpipe upgrades throughout building on floors indicated, as per plans filed herewith. No change t… |
| M01230963 ↗ | 222 EAST 64 STREET MANHATTAN | Alteration | Permit Issued | 07/30/2025 | 05/04/2026 | Design ICOR ASSOCIATES Contractor SIRINA FIRE PROT CORP | Northwell New MEETH Sprinkler / Standpipe modifications as per plans filed herewith. No change to use, occupancy or egress under this applic… |
| M01390346 ↗ | 855 PARK AVENUE MANHATTAN | Alteration | Permit Issued | 04/27/2026 | 05/04/2026 | Design LIZARDOS ENGINEERING Contractor L.F. DRISCOLL COMPANY LLC | Northwell Lenox Hill Chiller # 2 and # 3 Replacement Project: rearrange interior, non-bearing partition(s), install hung ceiling, wall and f… |
| Q01162581 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 03/18/2025 | 04/28/2026 | Design LIZARDOS ENGINEERING Owner NORTHWELL HEALTH Contractor SIRINA FIRE PROT CORP | Northwell Health LIJ Medical Center: Separation of Branches ECCC Phase: modify existing plumbing, sprinkler and standpipe systems to conform… |
| Q01372794 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Filed — no permit on record | 04/27/2026 | — | Design BURNS ENGINEERING, PC Owner NORTHWELL HEALTH | — |
| Q01372018 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Filed — no permit on record | 04/24/2026 | — | Design BURNS ENGINEERING, PC Owner NORTHWELL HEALTH | — |
| Q01372753 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Filed — no permit on record | 04/20/2026 | — | Design BURNS ENGINEERING, PC Owner NORTHWELL HEALTH | — |
| M00873518 ↗ | 222 EAST 64 STREET MANHATTAN | Alteration | Signed-off | 06/28/2023 | 04/02/2026 | Design LIZARDOS ENGINEERING Contractor CAPITAL CONTR P&H CORP | Northwell Health: Lab Relocation Project: modify Plumbing system @ portion of cellar and 1st floor to conform with new layouts; modify Sprin… |
| M01172986 ↗ | 855 PARK AVENUE MANHATTAN | Alteration | Permit Issued | 03/13/2025 | 03/24/2026 | Design LIZARDOS ENGINEERING Contractor AMERICON CONSTRUCTION INC. | Northwell Lenox Hill Biplane Project: modify HVAC system to conform with new layouts as per plans filed herewith. |
| Q01340120 ↗ | 70-09 AUSTIN STREET QUEENS | Alteration | Signed-off | 01/20/2026 | 01/21/2026 | Design BLADYKAS ENGINEERING, P.C. Contractor ADI CONTRACTING LLC | Northwell Health - LINAC Replacement: modify Mechanical infrastructure @ portion of 1st floor & roof, in conjunction with Linear Accelerator… |
| Q01340126 | 70-09 AUSTIN STREET QUEENS | Alteration | Signed-off | 01/12/2026 | 01/21/2026 | Design BLADYKAS ENGINEERING, P.C. Contractor VILLAGE P & H NY INC | Northwell Health - LINAC Replacement: minor plumbing scope in conjunction with Linear Accelerator equipment replacement as per plans filed h… |
| Q01340136 | 70-09 AUSTIN STREET QUEENS | Alteration | Signed-off | 01/12/2026 | 01/16/2026 | Contractor ADI CONTRACTING LLC | Northwell Health - LINAC Replacement: minor structural work in conjunction with Linear Accelerator equipment replacement, as per plans filed… |
| M01102596 ↗ | 222 EAST 64 STREET MANHATTAN | Alteration | Signed-off | 10/11/2024 | 01/09/2026 | Design PAMELA A. SMITH Contractor THE WHITING-TURNER CONTRA | Northwell New MEETH: Architectural scope in conjunction with Emergency Generator & Quick Connect Project, as per plans filed herewith. No ch… |
| M01231004 ↗ | 208 EAST 64 STREET MANHATTAN | Alteration | Signed-off | 07/10/2025 | 12/22/2025 | Contractor THE WHITING-TURNER CONTRA | Northwell Health Old MEETH: minor Architectural scope in conjunction with sprinkler upgrades throughout building on floors indicated, as per… |
| M00628021 ↗ | 855 PARK AVENUE MANHATTAN | Alteration | Permit Issued | 01/19/2022 | 12/10/2025 | Design JAROS BAUM & BOLLES Contractor CARDOZA PLUMBING WMBE | Lenox Hill Hospital Lachman 5th Floor Emergency Power project: modify plumbing & sprinkler systems to conform with interior renovations as p… |
| Q01219795 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 06/25/2025 | 12/10/2025 | Owner NORTHWELL HEALTH Contractor NYC FIRE SPRINKLER CORP | Northwell LIJ IR-8 Equipment Replacement Project: modify Plumbing & Sprinkler systems to conform with new layouts as per plans filed herewit… |
| M01222723 ↗ | 111 EAST 58 STREET MANHATTAN | Alteration | Signed-off | 08/20/2025 | 11/17/2025 | Design LIZARDOS ENGINEERING Owner TENBER ASSOCIATES, L.P. Contractor ADVANCED PLUMBING MECH | Northwell Executive Health Pain Management Project: modify Plumbing & Sprinkler systems to conform with new floor layout, as per plans filed… |
| M01282001 ↗ | 20 7 AVENUE MANHATTAN | Alteration | Signed-off | 09/18/2025 | 11/06/2025 | Design AKF ENGINEERS, LLP Contractor CENTRAL CONSULTING & CONT | Northwell Greenwich Village: STAT Lab project: Mechanical systems to remain. Re-balance existing air outlets and remove existing lab fume ho… |
| M01280595 ↗ | 855 PARK AVENUE MANHATTAN | Alteration | Signed-off | 09/26/2025 | 11/05/2025 | Design JAROS BAUM & BOLLES Contractor EMPIRE GENERAL CONTRACTIN | Lenox Hill Hospital: replacement in kind of Chiller in conjunction with hospital MRI, as per plans filed herewith. |
| M01101657 ↗ | 208 EAST 64 STREET MANHATTAN | Alteration | Permit Issued | 10/15/2024 | 11/03/2025 | Design LIZARDOS ENGINEERING Contractor BOILERMATIC WELDING INDUS | Northwell OLD MEETH Em Gen Project: installation/modification of mechanical infrastructure in conjunction with installation of new Emergency… |
| M01102545 ↗ | 222 EAST 64 STREET MANHATTAN | Alteration | Permit Issued | 10/15/2024 | 11/03/2025 | Design LIZARDOS ENGINEERING Contractor BOILERMATIC WELDING INDUS | Northwell New MEETH: Associated mechanical scope below roof in conjunction with Emergency Generator & Quick Connect Project, as per plans fi… |
| M01105557 ↗ | 222 EAST 64 STREET MANHATTAN | Alteration | Signed-off | 10/16/2024 | 11/03/2025 | Design LIZARDOS ENGINEERING Contractor BOILERMATIC WELDNG INDS I | Northwell New MEETH Emergency Generator & Quick Connect Project: installation of fuel oil piping at above premises, for new Emergency Genera… |
| M01106819 ↗ | 208 EAST 64 STREET MANHATTAN | Alteration | Signed-off | 10/18/2024 | 11/03/2025 | Design LIZARDOS ENGINEERING Contractor BOILERMATIC WELDNG INDS I | Northwell Old MEETH: Installation of new fuel oil piping, with basement Emergency Generator removal and relocation. See comments for details… |
| M01222255 ↗ | 111 EAST 58 STREET MANHATTAN | Alteration | Signed-off | 08/20/2025 | 11/03/2025 | Design PERKINS EASTMAN Owner TENBER ASSOCIATES, L.P. Contractor THE WHITING-TURNER CONTRA | Northwell Health: Executive Health Pain Management Program: rearrange interior, non-bearing partitions, install hung ceiling, wall and floor… |
| M01102408 ↗ | 208 EAST 64 STREET MANHATTAN | Alteration | Permit Issued | 10/11/2024 | 10/02/2025 | Design GILSANZ MURRAY STEFICEK LLP Contractor THE WHITING-TURNER CONTRA | Northwell Old MEETH: structural scope in conjunction with Emergency Generator & Quick Connect Project, as per plans filed herewith. |
| M01106572 ↗ | 222 EAST 64 STREET MANHATTAN | Alteration | Permit Issued | 10/11/2024 | 10/02/2025 | Design GILSANZ MURRAY STEFICEK LLP Contractor THE WHITING-TURNER CONTRA | Northwell Health New MEETH: Emergency Generator & Quick Connect Project: structural scope in conjunction with new Em Gen installation @ roof… |
| M01031778 ↗ | 208 EAST 64 STREET MANHATTAN | Alteration | Signed-off | 05/01/2024 | 09/22/2025 | Design ICOR ASSOCIATES Contractor CAPITAL CONTR P&H CORP | Northwell Health Old MEETH Ambulatory Surgery Exhaust project: minor interior modifications to plumbing and sprinkler systems to conform wit… |
| M01222706 ↗ | 111 EAST 58 STREET MANHATTAN | Alteration | Signed-off | 08/20/2025 | 09/12/2025 | Design LIZARDOS ENGINEERING Owner TENBER ASSOCIATES, L.P. Contractor THE WHITING-TURNER CONTRA | Northwell: Executive Health Pain Management Project: rearrange HVAC / Mechanical systems to conform with new floor layout, as per plans file… |
| M00872302 ↗ | 222 EAST 64 STREET MANHATTAN | Alteration | Signed-off | 06/13/2023 | 08/14/2025 | Design THE MCGUIRE GROUP ARCHITECTS Contractor CENTRAL CONSULTING & CONT | Northwell Health: Lab Relocation Project: rearrange interior, non-bearing partitions, install hung ceiling, wall & floor finishes, at portio… |
| Q01219392 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Permit Issued | 06/26/2025 | 08/01/2025 | Owner NORTHWELL HEALTH Contractor BOTTO MECHANICAL CORP | Northwell LIJ Medical Center: IR-8 Equipment Replacement: rearrange mechanical systems to conform with new layouts as per plans filed herewi… |
| M01211039 ↗ | 208 EAST 64 STREET MANHATTAN | Alteration | Signed-off | 06/05/2025 | 07/28/2025 | Contractor THE WHITING-TURNER CONTRA | Northwell Health Old MEETH: minor Architectural scope in conjunction with sprinkler upgrades throughout building on floors indicated, as per… |
| Q01219230 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 06/25/2025 | 07/28/2025 | Design GILSANZ MURRAY STEFICEK LLP Owner NORTHWELL HEALTH Contractor THE WHITING-TURNER CONTRA | Northwell LIJ Medical Center: IR-8 Equipment Replacement Project: structural scope (framing for medical equipment) in conjunction with this … |
| Q01219210 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 06/25/2025 | 07/21/2025 | Design PAMELA A. SMITH Owner NORTHWELL HEALTH Contractor THE WHITING-TURNER CONTRA | Northwell LIJ Medical Center: IR-8 Equipment Replacement Project: rearrange interior non-bearing partitions, install hung ceiling, wall & fl… |
| S00196510 ↗ | 475 SEAVIEW AVENUE STATEN ISLAND | Alteration | Signed-off | 08/12/2019 | 05/30/2025 | Contractor VAN ALPHEN BROTHERS INC | Northwell Health Staten Island University Hospital: install concrete pad on grade in open space on hospital-owned private property. This is … |
| M01173835 ↗ | 855 PARK AVENUE MANHATTAN | Alteration | Signed-off | 03/04/2025 | 04/22/2025 | Design LIZARDOS ENGINEERING Contractor CAPITAL CONTR P&H CORP | Northwell Lenox Hill Biplane project: modify plumbing & sprinkler systems to conform with new room layouts as per plans filed herewith. |
| Q01202401 ↗ | 102-01 66 ROAD QUEENS | Alteration | Filed — no permit on record | 04/18/2025 | — | Design BURNS ENGINEERING, PC Owner NORTHWELL HEALTH | — |
| Q01208420 ↗ | 102-01 66 ROAD QUEENS | Alteration | Filed — no permit on record | 04/18/2025 | — | Design BURNS ENGINEERING, PC Owner NORTHWELL HEALTH | — |
| M01172940 ↗ | 855 PARK AVENUE MANHATTAN | Alteration | Signed-off | 03/04/2025 | 04/14/2025 | Contractor AMERICON CONSTRUCTION INC. | Northwell Lenox Hill - Biplane Project: rearrange interior, non-bearing partitions, install hung ceiling, wall & floors finishes as per plan… |
| M01173842 ↗ | 855 PARK AVENUE MANHATTAN | Alteration | Signed-off | 03/04/2025 | 04/14/2025 | Design GILSANZ MURRAY STEFICEK LLP Contractor AMERICON CONSTRUCTION INC. | Northwell Lenox Hill Biplane Project: structural work in conjunction with installation of medical equipment, as per plans filed herewith. |
| Q01157603 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Permit Issued | 03/18/2025 | 04/14/2025 | Design LIZARDOS ENGINEERING Owner NORTHWELL HEALTH Contractor CONSIGLI CONSTRUCTION CO | Northwell LIJ Medical Center: Separation of Branches ECCC Phase: rearrange existing Mechanical systems to conform with new layouts as per pl… |
| M00994719 ↗ | 204 EAST 77 STREET MANHATTAN | Alteration | Signed-off | 02/12/2024 | 03/11/2025 | Contractor CONSIGLI CONSTRUCTION CO | Lot Line Exterior Masonry Window Opening Infill work, at Westerly lot line adjacent to 3rd Ave corner Lot # 46, No Change in Use Egress or O… |
| M00949025 ↗ | 20 7 AVENUE MANHATTAN | Alteration | Signed-off | 01/02/2024 | 02/25/2025 | Design AKF ENGINEERS, LLP Contractor SIRINA FIRE PROT CORP | Northwell Lenox Hill: Cardio Cath Lab Suite & Inpatient Care project: modify plumbing & sprinkler systems to conform to new room layouts as … |
| Q01154673 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 02/03/2025 | 02/21/2025 | Design THE LIRO GROUP Owner NORTHWELL HEALTH Contractor CURRENT FIRE PROTECTION I | Northwell LIJ: LINAC Project: modify existing plumbing & sprinkler systems to conform with new medical suite equipment installation as per p… |
| Q01153421 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 01/22/2025 | 02/19/2025 | Design PAMELA A. SMITH Owner NORTHWELL HEALTH Contractor CONSIGLI CONSTRUCTION CO | LIJ Northwell Health: LINAC Project: rearrange interior non-bearing partitions, install hung ceiling, wall & floor finishes @ portion of cel… |
| Q01153434 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 01/22/2025 | 02/19/2025 | Design GILSANZ MURRAY STEFICEK LLP Owner NORTHWELL HEALTH Contractor CONSIGLI CONSTRUCTION CO | LIJ Northwell Health: LINAC Project: installation of structural support systems and concrete pad for new medical equipment, as per plans fil… |
| Q01153509 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 02/03/2025 | 02/19/2025 | Design THE LIRO GROUP Owner NORTHWELL HEALTH Contractor CONSIGLI CONSTRUCTION CO | LIJ Northwell Health: LINAC Project: modify existing Mechanical systems to conform with new suite layout due to replacement of LINAC equipme… |
| M01064700 ↗ | 855 PARK AVENUE MANHATTAN | Alteration | Signed-off | 11/18/2024 | 02/06/2025 | Design EWINGCOLE Contractor EMPIRE GENERAL CONTRACTIN | Northwell Lenox Hill Hospital: Wollman Lachman Project: rearrange interior, non-bearing partitions, install hung ceiling, wall & floor fini… |
| M00924977 ↗ | 20 7 AVENUE MANHATTAN | Alteration | Signed-off | 10/18/2023 | 01/21/2025 | Design AKF ENGINEERS, LLP Contractor SIRINA FIRE PROT CORP | Northwell Lenox Hill: Cardio Cath Lab Suite & Inpatient Care project: modify plumbing & sprinkler systems to conform to new room layouts as … |
| Q01014333 ↗ | 102-01 66 ROAD QUEENS | Alteration | Signed-off | 04/30/2024 | 12/13/2024 | Design LANG ENGINEERING P.C. Owner NORTHWELL HEALTH Contractor ISLAND ACOUSTICS LLC | Forest Hills Hospital: Central Sterile Supply Project: minor structural scope in conjunction with project as per plans filed herewith. |
| M01102365 ↗ | 208 EAST 64 STREET MANHATTAN | Alteration | Signed-off | 10/11/2024 | 12/05/2024 | Design PAMELA A. SMITH Contractor THE WHITING-TURNER CONTRA | Northwell Old MEETH: Architectural scope in conjunction with Emergency Generator & Quick Connect Project, as per plans filed herewith. No ch… |
| Q01121555 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 10/17/2024 | 11/22/2024 | Owner NORTHWELL HEALTH Contractor MACCARONE PLUMBING INC | Northwell Health LIJ Medical Center: Combo Lab Project: modify existing Plumbing and Sprinkler systems to confirm with new layouts as per pl… |
| Q01121474 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 10/18/2024 | 11/20/2024 | Owner NORTHWELL HEALTH Contractor BOTTO MECHANICAL CORP | Northwell Health LIJ Medical Center: Combo Lab Project: modify existing Mechanical systems to conform with new layouts as per plans filed he… |
| Q01121439 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 10/17/2024 | 11/13/2024 | Design PAMELA A. SMITH Owner NORTHWELL HEALTH Contractor THE WHITING-TURNER CONTRA | Northwell Health LIJ Medical Center: Combo Lab project: rearrange interior, non-bearing partitions, install hung ceiling and wall and floor … |
| M01121736 ↗ | 855 PARK AVENUE MANHATTAN | Alteration | Signed-off | 10/28/2024 | 11/01/2024 | Design GILSANZ MURRAY STEFICEK LLP Contractor CENTRAL CONSULTING & CONT | Northwell Health Lenox Hill Cath Lab B: installation of framing (including Unistrut) & related scope at portion of 11th floor, for support o… |
| Q01121512 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 10/16/2024 | 10/25/2024 | Design GILSANZ MURRAY STEFICEK LLP Owner NORTHWELL HEALTH Contractor THE WHITING-TURNER CONTRA | Northwell Health LIJ Medical Center: Combo Lab Project: minor Structural scope (framing for support of medical equipment) in conjunction wit… |
| Q01065638 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 07/10/2024 | 10/16/2024 | Design LANGAN ENGINEERING Owner NORTHWELL HEALTH Contractor THE WHITING-TURNER CONTRA | Northwell LIJ Medical Center - Zucker Hillside Campus: Kaufman IP Project: civil site work including grading, installation of handrails, and… |
| Q01073164 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 08/20/2024 | 10/14/2024 | Design THE LIRO GROUP Owner NORTHWELL HEALTH Contractor ADI CONTRACTING LLC | Northwell Health LIJ Medical Center - Doctor's On Call project: modify Mechanical systems to conform with new layouts. |
| Q01070939 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 07/10/2024 | 10/09/2024 | Design PAMELA A. SMITH Owner NORTHWELL HEALTH Contractor ADI CONTRACTING LLC | Doctor's On Call: rearrange interior, non-bearing partitions, install hung ceiling, wall and floor finishes as per plans filed herewith. No … |
| Q01052680 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 06/26/2024 | 10/08/2024 | Design BLADYKAS ENGINEERING, P.C. Owner NORTHWELL HEALTH Contractor THE WHITING-TURNER CONTRA | Northwell LIJ Medical Center Zucker Hillside Campus - Kaufman IP Project: modify Mechanical/HVAC systems to conform to new layouts as per pl… |
| Q01052753 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 06/19/2024 | 09/11/2024 | Design BLADYKAS ENGINEERING, P.C. Owner NORTHWELL HEALTH Contractor SIRINA FIRE PROT CORP | Northwell LIJ Medical Center Zucker Hillside Campus - Kaufman IP Project: modify plumbing and sprinkler systems to conform with new layouts … |
| M01031774 ↗ | 208 EAST 64 STREET MANHATTAN | Alteration | Signed-off | 05/01/2024 | 09/06/2024 | Design THE MCGUIRE GROUP ARCHITECTS Contractor CENTRAL CONSULTING & CONT | Northwell Health Old MEETH Ambulatory Surgery Exhaust Project: rearrange interior non-bearing partitions, install hung ceiling, wall and flo… |
| Q01045935 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 08/01/2024 | 09/03/2024 | Design AKF ENGINEERS, LLP Owner NORTHWELL HEALTH Contractor MACCARONE PLUMBING INC | Northwell LIJ O.R. Hybrid Project: modify Plumbing and Sprinkler systems to conform with new room layouts as per plans filed herewith. |
| Q01053322 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 07/10/2024 | 08/27/2024 | Design LANGAN ENGINEERING Owner NORTHWELL HEALTH Contractor MACCARONE PLUMBING INC | Northwell LIJ Medical Center Zucker Campus - Kaufman IP Project: Civil plumbing scope in conjunction with project, as per plans filed herewi… |
| Q00487974 ↗ | 102-01 66 ROAD QUEENS | Alteration | Signed-off | 04/07/2021 | 08/20/2024 | Design LIZARDOS ENGINEERING Owner NORTHWELL HEALTH Contractor CARDOZA PLUMBING WMBE | Northwell Health Forest Hill Hospital: plumbing work associated with replacement of low pressure steam domestic hot water heaters, as per pl… |
| Q00909064 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 09/12/2023 | 08/20/2024 | Design LOTHROP ASSOCIATES Owner NORTHWELL HEALTH Contractor B & A RESTORATION CONTRA | Northwell LIJ Sloman Bldg: partial roof repair/replacement, including parapet, as per plans filed herewith. |
| Q01045913 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 07/31/2024 | 08/20/2024 | Design AKF ENGINEERS, LLP Owner NORTHWELL HEALTH Contractor GILBANE BUILDING COMPANY | Northwell LIJ O.R. Hybrid Project: modify Mechanical/HVAC systems to conform with new room lay-outs as per plans filed herewith. |
| Q01012737 ↗ | 102-01 66 ROAD QUEENS | Alteration | Signed-off | 04/24/2024 | 07/31/2024 | Design LIZARDOS ENGINEERING Owner NORTHWELL HEALTH Contractor SIRINA FIRE PROT CORP | Forest Hills Hospital: Central Sterile Supply Project: modify plumbing and sprinkler systems to conform with new room layouts as per plans f… |
| S01045721 ↗ | 475 SEAVIEW AVENUE STATEN ISLAND | Alteration | Signed-off | 06/13/2024 | 07/29/2024 | Design SHANE R. HAMILTON Owner NORTHWELL HEALTH (SIUH) Contractor EMPIRE GENERAL CONTRACTIN | Northwell Health SIUH: EP Lab Project: modify Mechanical/HVAC system to conform with new layouts, as per plans filed herewith. |
| S08002327 ↗ | 375 SEGUINE AVENUE STATEN ISLAND | Alteration | Signed-off | 10/24/2022 | 07/25/2024 | Design P.W. GROSSER CONSULTING Owner NORTHWELL HEALTH (SIUH) Contractor AMERICAN BOILER & WELDING | Northwell S.I.U.H: installation (replacement in kind) of 30,000 gallon double-walled underground fuel oil storage tank & associated piping t… |
| Q01052639 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 06/20/2024 | 07/11/2024 | Owner NORTHWELL HEALTH Contractor THE WHITING-TURNER CONTRA | Northwell LIJ Medical Center Zucker Hillside Campus - Kaufman IP Project: rearrange interior, non-bearing partitions, install hung ceiling,… |
| Q01055072 ↗ | 270-05 76 AVENUE QUEENS | Alteration | Signed-off | 06/14/2024 | 07/10/2024 | Design GILSANZ MURRAY STEFICEK LLP Owner NORTHWELL HEALTH Contractor THE WHITING-TURNER CONTRA | Northwell LIJ Medical Center - Zucker Hillside Campus: Kaufman IP Project: minor structural scope in conjunction with project as per plans f… |
| M00949016 ↗ | 20 7 AVENUE MANHATTAN | Alteration | Signed-off | 11/22/2023 | 07/03/2024 | Design AKF ENGINEERS, LLP Contractor CENTRAL CONSULTING & CONT | Northwell Lenox Hill: Cardio Cath Lab Suite & Inpatient Care project: modify mechanical systems to conform to new interior modifications as … |
| M00917131 ↗ | 20 7 AVENUE MANHATTAN | Alteration | Signed-off | 09/26/2023 | 07/02/2024 | Design PAMELA A. SMITH Contractor CENTRAL CONSULTING & CONT | Northwell Lenox Hill: Cardio Cath Lab Suite & Inpatient Care: rearrange interior non-bearing partitions, install wall & floor finishes, hung… |
| Building | Filings | Most Recent |
|---|---|---|
| 1345 3 AVENUE ↗ | 34 | 09/11/2026 |
| 208 EAST 64 STREET ↗ | 23 | 08/13/2026 |
| 222 EAST 64 STREET ↗ | 20 | 07/28/2026 |
| 20 7 AVENUE ↗ | 26 | 06/29/2026 |
| 95-25 QUEENS BOULEVARD ↗ | 4 | 05/14/2026 |
| 855 PARK AVENUE ↗ | 26 | 04/21/2026 |
| 111 EAST 58 STREET ↗ | 4 | 04/02/2026 |
| 270-05 76 AVENUE ↗ | 11 | 03/23/2026 |
| 270-05 76 AVENUE ↗ | 33 | 03/16/2026 |
| 270-05 76 AVENUE ↗ | 3 | 03/16/2026 |
| 70-09 AUSTIN STREET ↗ | 3 | 12/26/2025 |
| 1482 3 AVENUE ↗ | 5 | 09/19/2025 |
| 270-05 76 AVENUE ↗ | 16 | 09/04/2025 |
| 264-25 76 AVENUE ↗ | 10 | 06/02/2025 |
| 102-01 66 ROAD ↗ | 17 | 04/09/2025 |
| 475 SEAVIEW AVENUE ↗ | 25 | 01/07/2025 |
| 375 SEGUINE AVENUE ↗ | 11 | 08/29/2024 |
| 270-05 76 AVENUE ↗ | 2 | 06/24/2024 |
| 204 EAST 77 STREET ↗ | 1 | 01/23/2024 |
| 205 EAST 76 STREET ↗ | 1 | 01/23/2024 |
| 270-05 76 AVENUE ↗ | 6 | 09/22/2023 |
| 1421 3 AVENUE ↗ | 6 | 05/05/2023 |
| 270-05 76 AVENUE ↗ | 3 | 11/21/2022 |
| 102-01 66 ROAD ↗ | 1 | 06/24/2021 |
| 2301 BOARDWALK WEST ↗ | 2 | 12/18/2020 |
| 430 EAST 29 STREET ↗ | 1 | 07/24/2020 |
| 200-14 44 AVENUE ↗ | 2 | 04/29/2020 |
| 50-01 2 STREET ↗ | 1 | 01/02/2020 |
| 120 WATER STREET ↗ | 1 | 08/15/2019 |
| 50 BROADWAY ↗ | 2 | 07/24/2019 |